Skip to main content

AgendaQuick™

View Agenda Item

Action   4.
Flood Control District Meeting
Engineering & Natural Resources
Meeting Date:
10/13/2020
Title:
MOU with City of Sierra Vista for Feasibility Recharge Facility
Submitted By:
Teresa Garcia, Engineering & Natural Resources
Department:
Engineering & Natural Resources
Presentation:
No A/V Presentation
Recommendation:
Approve
Document Signatures:
BOS Signature Required
# of ORIGINALS
Submitted for Signature:
2
NAME
of PRESENTER:
Jackie Watkins, P.E
TITLE
of PRESENTER:
Director Engineering & Nat. Resources
Mandated Function?:
Federal or State Mandate
Source of Mandate
or Basis for Support?:
Docket Number (If applicable):

Information

Agenda Item Text:

Approve Memorandum of Understanding (MOU) between The Nature Conservancy, Cochise County, and the City of Sierra Vista, for a Feasibility Recharge Facility on the 1,811-acres Riverstone property, in the amount of $125,000, effective October 1, 2020 through May 1, 2021.

Background:

The parties have identified the 1,811-acre Riverstone property owned by the County as a possible location for a recharge facility, and have identified the water source to be recharged as treated effluent conveyed from the City’s Environmental Operations Park wastewater treatment facility.

Department's Next Steps (if approved):

Process MOU as requested

Impact of NOT Approving/Alternatives:

Funding cost for City of Sierra Vista Recharge Feasibility Study will not be funded by $125,000 as a result of not approving MOU.

To BOS Staff: Document Disposition/Follow-Up:

After approval, two agreement to be signed and returned to Teresa Garcia

Fiscal Impact

Fiscal Year:
FY21
One-time Fixed Costs? ($$$):
125000

Fiscal Impact & Funding Sources (if known):

Flood Control District 258-4100-4107-421.000