Action   18.
Regular Board of Supervisors Meeting
Development Services
Meeting Date:
12/14/2021
Title:
Change Order with Pavex Corp. - Cochise County Airport Apron Reconstruction
Submitted By:
Dan Coxworth, Development Services
Department:
Development Services
Presentation:
No A/V Presentation
Recommendation:
Approve
Document Signatures:
BOS Signature Required
# of ORIGINALS
Submitted for Signature:
0
NAME
of PRESENTER:
Dan Coxworth
TITLE
of PRESENTER:
Director
Docket Number (If applicable):
Mandated Function?:
Not Mandated
Source of Mandate
or Basis for Support?:

Information

Agenda Item Text:

Approve a Change Order to Construction Services Contract No. IFB 21-21-DEV-01 with Pavex Corp., in the amount of $78,388.87, for work associated with the reconstruction of the apron at the Cochise County Airport in Willcox.

Background:

This project is an FAA (Federal Aviation Administration) 100% grant-funded project. The increase in cost is due to the removal of concrete blocks that were discovered during the excavation of the apron.  Please see attached Attachment "U", Contract Change Order No. 1 for justification of the change. 

The total amount of Contract No. IFB 21-21-DEV-01 with Pavex Corp, approved by the Board of Supervisors in the amount of $1,261,670, will be increased to $1,340,058.87.

Department's Next Steps (if approved):

Provide signed change order to the contractor. 

Impact of NOT Approving/Alternatives:

The contract will not be amended.

To BOS Staff: Document Disposition/Follow-Up:

Nothing.  Approval by the Board will allow the County staff to sign the change order to the contract. 

Attachments