Action   12.
Regular Board of Supervisors Meeting
Development Services
Meeting Date:
04/19/2022
Title:
Contract with Progressive Roofing - Repair the Large Hanger at BDI Airport
Submitted By:
Dan Coxworth, Development Services
Department:
Development Services
Presentation:
No A/V Presentation
Recommendation:
Approve
Document Signatures:
BOS Signature NOT Required
# of ORIGINALS
Submitted for Signature:
0
NAME
of PRESENTER:
Dan Coxworth
TITLE
of PRESENTER:
Director
Docket Number (If applicable):
Mandated Function?:
Not Mandated
Source of Mandate
or Basis for Support?:

Information

Agenda Item Text:

Approve Contract with Progressive Roofing to repair the roof of the large hanger located at the Bisbee-Douglas International Airport, in the amount of $40,889.02. 

Background:

The roof of the large hander at BDI was recently damaged by a wind storm.  The cost to replace the roof is $400,000. Instead of replacing, staff has decided to repair the damage. This project will be funded from half-cent sales tax in the County Capital Fund (400) and transferred to the Airport Enterprise Fund (105).

Department's Next Steps (if approved):

Create a purchase order and schedule the repair.

Impact of NOT Approving/Alternatives:

The roof will not be repaired and further damage to the structure may occur. 

To BOS Staff: Document Disposition/Follow-Up:

None