Action   13.
Regular Board of Supervisors Meeting - 10:00 am
Facilities
Meeting Date:
01/27/2026
Title:
Funding for VRV Retrofit for the Bisbee Admin Building
Submitted By:
Jackie McElyea, Facilities
Department:
Facilities
Presentation:
No A/V Presentation
Recommendation:
Approve
Document Signatures:
BOS Signature NOT Required
# of ORIGINALS
Submitted for Signature:
0
NAME
of PRESENTER:
Darrel Crowley
TITLE
of PRESENTER:
Facilities Director
Mandated Function?:
Not Mandated
Source of Mandate
or Basis for Support?:
Docket Number (If applicable):

Information

Agenda Item Text:

Approve the transfer of County Capital Projects Contingency to the Facilities Department to install 10 VRV Condensers and 4 Air Handlers at the Bisbee Administration Building at 4 Ledge Avenue, in the amount of $1,909,068.

Background:

The existing boiler and air handlers need to be demolished and replaced with an alternative due to their old age. It is the Facilities Management Department’s recommendation to replace the current system to prevent further system failure.

Department's Next Steps (if approved):

Move funds from contingency, issue a purchase order to Midstate Mechanical, and begin scheduling the work.

Impact of NOT Approving/Alternatives:

The current system will continue to fail, leaving occupants without proper cooling or heat.

To BOS Staff: Document Disposition/Follow-Up:

No follow-up from the BOS staff is needed.

Fiscal Impact

Fiscal Year:
FY26
One-time Fixed Costs? ($$$):
$1,909,068.00
Source of Funding?:
Contingency

Fiscal Impact & Funding Sources (if known):

Requesting County Capital Projects Contingency (400-1400-9 491.100).

Attachments