Approval of Amendment 1 to Project Tri-Party Agreement between Broward Metropolitan Authority (MPO), City of Pembroke Pines and MTECC for Project 4334293, City of Pembroke Pines Mobility Hub to increase the Federal grant budget.
 

WHAT THIS ACTION ACCOMPLISHES:

The Federal Transit Administration through the Broward MPO have increase the Federal Transit Administration funding for Project 4334293 by $247,752.  This action amends the Project Tri-Party Agreement between Broward MPO, City of Pembroke Pines and MTECC to increase the project budget and Federal grant funding by $247,752.
 

SUMMARY EXPLANATION/BACKGROUND:

The Federal Transit Administration Grant with Broward MPO includes multiple projects that include Project 4334293, City of Pembroke Pines Mobility Hub.One of the other projects included in the grant was nearing completion and did not need all the funds allocated to the project.
 
The budget for the City of Pembroke Pines Mobility Hub is very tight and the scope was adjusted to limit lighting to a select few locations.The increase in the project budget of $247,752 will provide additional lighting locations for the project to increase safety and nighttime use of the Mobility Hub locations.
 
The City of Pembroke Pines approved Amendment 1 to the Project Tri-Party Agreement in May 2025.The Broward MPO has Amendment 1 to the Project Tri-Party Agreement on their consent agenda for June 12, 2025.
 

MTECC STAFF RECOMMENDATION(S):

Recommend approval of Amendment 1 to the Project Tri-Party Agreement for Project 4334293, City of Pembroke Pines Mobility Hub, subject to action by the Broward MPO.
 