- Meeting Date:
- 06/18/2013
- Submitted For:
- Trevor Henry, Project Manager
- From:
- Trevor Henry, Project Manager
Information
TITLE:
RECOMMENDED ACTION:
1) Award the construction contract to Seller’s and Sons, Inc. of Glendale, Arizona in the total award amount of $980,483, which includes $25,000 in contract allowance. The contract period is 120 calendar days; and
2) Authorize Change Order Authority to the City Manager in the amount of $95,550 (10% of the bid contract amount, less contract allowance) for unanticipated additional costs; and
3) Authorize the City Manager to execute the necessary documents.
Policy Decision or Reason for Action:
Awarding the contract will authorize the construction of the Switzer Canyon Transmission Main Project in accordance with the approved public improvements construction plans prepared by Turner Engineering, Inc.
Financial Impact:
The Switzer Canyon Transmission Main project is funded by the total budget appropriation of $1,165,554 (includes FY 12 and FY 13 prior year expenditures) and FY 14 budget amount of $1,020,483 (acct. 201-5120-770).
Connection to Council Goal:
Repair, replace, maintain infrastructure (streets & utilities)
Has There Been Previous Council Decision on This:
No.
Options and Alternatives:
- Approve the award as recommended.
- Reject the approval of the award and direct staff to re-advertise the project. This option would delay the construction start date and cause the work to be deferred until 2014.
Background/History:
Construction impacts may include traffic detours, temporary lane closures with traffic flagging and temporary access to parcels with signage. Coordination with property and business owners will be made for water service disconnects and reconnects.
Key Considerations:
| Bidder |
Total |
| Engineer’s Estimate |
$ 859,688.00 |
| Seller’s and Sons |
$ 980,483.00 |
| Alliance Street Works |
$ 1,099,500.00 |
| LP’s Excavating |
$ 1,118,943.00 |
| Red Point |
$ 1,217,984.00 |
| McDonald Brothers |
$ 1,249,914.00 |
| Fann Contracting |
$ 1,308,299.00 |
| RTR Paving and Resurfacing Inc. |
$ 1,411,917.00 |
| RK Sanders Inc. |
$ 1,430,491.00 |
| CLM Earthworks |
$ 1,433,570.10 |
| Standard Construction Co. |
$ 1,444,391.00 |
| Eagle Mountain Construction, Inc |
$ 1,628,996.00 |
| Hunter Contracting |
$ 1,786,233.00 |
| Gantry Construction |
$ 1,979,015.00 |
Expanded Financial Considerations:
Community Benefits and Considerations:
Community Involvement:
Expanded Options and Alternatives:
- Approve the award as recommended.
- Reject approval of the award. This option would delay the construction start and cause the work to be deferred until 2014.