TITLE:

Consideration and Approval of Grant Agreement:  Approve the Grant Agreement between the City of Flagstaff and Arizona Department of Transportation, Multimodal Planning Division Aeronautics Group for the Aircraft Parking Ramp Joint Repairs

RECOMMENDED ACTION:

Approve the Grant Agreement between the City of Flagstaff and Arizona Department of Transportation, Multimodal Planning Division Aeronautics Group.

Policy Decision or Reason for Action:

Subsidiary Decision Points: This grant will assist with the costs associated with joint repairs between aircraft parking ramp concrete slabs to include replacing backer rod spacers and permanently sealing joints (approximately 30,508 square yards) for the improvement of the Flagstaff Pulliam Airport.

Financial Impact:

The Grant Agreement is a 90-10 match, totaling $310,000.  The ADOT grant award amount is $279,000 and requires a City match of $31,000 for a total project cost of $310,000.

Connection to Council Goal:

Repair Replace maintain infrastructure (streets & utilities)
Effective governance

Has There Been Previous Council Decision on This:

No

Options and Alternatives:

A.  Approve the Grant Agreement and prolong the life of the concrete ramp.
B.  Do not approve the Grant Agreement and pay for the entire cost of the project out of the City's Capital Improvement Program.
C.  Do not approved the Grant Agreement, nor perform the work and risk concrete deterioration/failure.



Background/History:

The ultra violet rays are deteriorating existing silicone seals in the concrete joints, and the Airport sweeper is exacerbating the problem.  Joints will soon contain no sealant, resulting in dangerous concrete block heave issues during moist freeze thaw cycles.

Key Considerations:

The concrete ramp repairs will allow the City to continue to provide safe on and off ramp loading for airline passengers.

Expanded Financial Considerations:

The total grant award amount is $279,000 (90% of total project cost) with a City match in the amount of $31,000 (10% of total project cost) for a total project cost of $310,000.  The project is budgeted in FY 2014 in account number 270-3724-783-4103.

Community Benefits and Considerations:

Construction of the project will increase the utility and safety of operations at the Airport, as well as provide continued commercial air service on a safely constructed ramp.

Community Involvement:

Inform - Construction of these improvements is included as part of the Federal Aviation Administration (FAA) approved Pulliam Airport Master Plan which was also approved by the City Council on June 20, 2000.  Approval of the Master Plan included numerous public meetings and hearings where public input was actively solicited.  In addition, the Airport Commission has had involvement in reviewing the overall project as part of the Airport project updates which are discussed at the Commission’s regularly scheduled monthly meetings.