- Meeting Date:
- 07/07/2020
- Co-Submitter:
- Stacey Brechler-Knaggs
- From:
- Adam Miele, Senior Project Manager
Information
TITLE:
STAFF RECOMMENDED ACTION:
- Approve a Professional Architectural Design Services Contract with APMI, Inc. for the programing and design phased services in the amount of $859,977 with a contract time of 365 calendar days; and
- Authorize the City Manager to execute the necessary documents.
Executive Summary:
Financial Impact:
Policy Impact:
Connection to Council Goal, Regional Plan, CAAP, and/or Strategic Plan:
Has There Been Previous Council Decision on This:
Yes. Council in 2018 (December) was presented with the updated airport master plan that identified the need and recommended location for the new facility.
Options and Alternatives:
- Authorize the acceptance of the Contract from APMI, Inc. for professional services.
- Reject the acceptance of the Contract from APMI, Inc. for professional services and re-solicit for the services.
- Reject the Contract and continue existing operations in the existing facility.
Background and History:
The newly updated master plan indicates the need to centralize the snow removal equipment away from fire operations. Due to the addition of the second commercial carrier, the federal requirements for winter operations (snow removal) require additional removal equipment and more stringent service times. In order to achieve the federal requirements, additional operations equipment was ordered.
Per Arizona State Law, a Request for Statement of Qualifications (RSOQ) solicitation was used to select the Design firm. A five-person evaluation committee was established that consisted of four (4) City staff, one of which is a registered engineer, one of which is a registered architect and one (1) principal of a commercial licensed general contractor. Specific evaluation criteria were provided within the RSOQ and were used by the committee during the selection process.
Procurement and the review panel conducted an initial review of all six (6) proposals for responsiveness to the requirement presented in the RSOQ. All six (6) proposals were accepted and passed on to the evaluation committee.
Key Considerations:
The solicitation for the contractor was very successful and generated six (6) interested bids. The highest scored design professional is very much aware of the preferred design/construction timeline. The contractor is confident the project will be completed on time and on budget.
Community Involvement:
Expanded Options and Alternatives:
Consult – Staff will continue to share the design progress with the airport commission as well as City Council.
Empower – The Federal Aviation Administration and City Council have been very supportive of the project.