- Meeting Date:
- 04/04/2017
- From:
- Trevor Henry, Project Manager
Information
TITLE:
RECOMMENDED ACTION:
2) Approve Change Order Authority to the City Manager in the amount of $123,000.00 (10% of the contract amount, less allowances)
3) Authorize the City Manager to execute the necessary documents.
Executive Summary:
Financial Impact:
Policy Impact:
Connection to Council Goal, Regional Plan and/or TeamFlagstaff Strategic Plan:
3) Provide sustainable and equitable public facilities, services, and infrastructure systems in an efficient and effective manner to serve all population areas and demographics
Has There Been Previous Council Decision on This:
Options and Alternatives:
2. Reject all bids. This action would delay the Project. If rejection occurs, possible options Include:
a) Re-solicit the Project at a later date;
b) Suspend or cancel the Project.
Background and History:
The Project has a general scope to upgrade the existing water mains, services and fire hydrants on Grand Canyon Avenue, Spring Street and Coconino Avenue combined. The Project will also replace damaged concrete curb, gutter and sidewalks within the Project limits. Grand Canyon Avenue will receive a mill and asphalt overlay, Spring Street will have a complete rebuild of the roadway section, Coconino Avenue will receive only the standard trench asphalt pavement patch.
Construction impacts may include traffic detours, temporary lane closures with traffic flagging and temporary access to parcels with signage. Coordination with property owners will be made for water service disconnects and reconnects.
With Council approval of the Contract, work is scheduled to begin as soon as weather allows in 2017. The Project is included in a Fund that has been programmed in the Capital Improvement 5-year plan.
The Purchasing section posted the Invitation for Bids (IFB) solicitation for construction on January 11, 2017 on the City website and Purchasing's electronic bidding website, and advertised in the newspaper on January 22nd and February 5th, 2017. There were five bids received on the opening date of February 23, 2017 and staff determined that McDonald Brothers Construction, Inc. is the lowest responsive and responsible bidder.
Key Considerations:
Community Benefits and Considerations:
| McDonald Brothers Construction, Inc. | $1,294,248,28 |
| Sellers and Sons, Inc. | $1,371,008.85 |
| Kinkaid Civil Construction | $1,427,190.15 |
| Engineer's Estimate | $1,522,12.70 |
| Fann Contracting, Inc. | $1,594,396.85 |
| Standard Construction Co., Inc. | $1,652,037.30 |
Included in the Contract amount will be an allowance of $65,000.00. The allowance will be used for items of work that are necessary to complete the Project that may have been an oversight at the time of the design. The project manager, section head and department head will have the authority to approve the use of the allowance.
Change Order Authority establishes a dollar amount (10% of the contract amount, less allowance) and provides the City Manager, on behalf of the Council, authority to amend the contract amount in response to unforeseen costs that are more than the contracted amount and in excess of the contract allowance.