There have been four previous IGA/JPA’s for this project:
- Original IGA/JPA was for the inventory of all signs citywide.
- Second was for the design and installation of Phase I
- Third was for the design of Phase II
- Fourth was for the installation of Phase II.
Approving this IGA/JPA will obligate Federal HSIP funding in the amount of $290,797.00 for the design and installation of Phase III - the final phase of the sign replacement program. Of the 4,600 signs, there are approximately 2,800 street signs (Street Names) located throughout the City. For this reason a map book of the entire City is produced with each sign having a unique Sign ID. There is a database for the sign program located in the S: Drive-Information Technology-GIS Section-Shared GIS Resources-Layer Files-Signs and Posts. Attachments for this staff report include an example of the Map Book cover sheet and a single map page from the Phase II documents.
Financial Impact:
Policy Impact:
Connection to Council Goal, Regional Plan and/or TeamFlagstaff Strategic Plan:
Transportation and Other Public Infrastructure:
Deliver quality community assets and continue to advocate and implement a highly performing multi-modal transportation system.
REGIONAL PLAN:
Goal T.8. Establish a functional, safe, and aesthetic hierarchy of roads and streets.
TEAM FLAGSTAFF STRATEGIC PLAN:
SP#3: Enhance that organization's fiscal stability and resourcefulness.
Has There Been Previous Council Decision on This:
- Original IGA/JPA for FY 2010 HSIP funds awarded on July 20, 2010
- Amendment One approved on June 10, 2011
- An IGA/JPA was approved in November 2013 for design and installation of Phase I.
- An IGA/JPA for the design for Phase II was approved on June 8, 2015.
- An IGA/JPA for the installation of Phase II was approved on October 6, 2015
Options and Alternatives:
2. Reject IGA/JPA
Background and History:
Key Considerations:
Community Benefits and Considerations:
The sign replacement funding per fiscal year are in the following amounts:
- FY 2014 - $300,000
- FY 2016 - $297,000
- FY 2018 - $290,797
The total cost of the sign replacement plan is estimated to be $887,797.00 and will be paid for from HSIP funds. The federal share is funded at $887,797.00 (100%).
Community Involvement:
Expanded Options and Alternatives:
Inform:
This project has been approved by the Flagstaff Metropolitan Planning Organization for inclusion in the Transportation Improvement Program.