- Meeting Date:
- 04/16/2013
- Submitted For:
- Trevor Henry, Project Manager
- From:
- Trevor Henry, Project Manager
Information
TITLE:
RECOMMENDED ACTION:
1) Award the construction contract to Eagle Mountain Construction of Flagstaff, Arizona in the amount of $158,475.00, which includes $16,000.00 in contract allowance. The contract period is 60 calendar days; and
2) Authorize Change Order Authority to the City Manager in the amount of $14,300.00 (10% of the bid contract amount, less contract allowance) for unanticipated additional costs; and
3) Authorize the City Manager to execute the necessary documents.
Policy Decision or Reason for Action:
Award of the contract will authorize the construction of the Sitgreaves ADA Ramp, Milton Rd to Santa Fe Avenue project in accordance with the approved public improvements.
Decision points: Proceeding with the contract work will improve the pathway and provide safety and ADA-compliant access to pedestrian traffic as an alternative to the existing staircase.
Financial Impact:
The project is funded in the amount of $206,500 from the Transportation Tax Revenues for FY13. This project is funded in part from the Federal Highway Administration (FHWA) through the Arizona Department of Transporation (ADOT) and will be share in the project construction cost.
Connection to Council Goal:
Repair Replace maintain infrastructure (streets & utilities)
Has There Been Previous Council Decision on This:
Options and Alternatives:
- Approve the award as recommended
- Reject bids and re-advertise the project, which could forfeit the ADOT Money and necessitate the suspension or cancellation of the project.
Background/History:
Key Considerations:
| Bidder |
Total |
| Engineer’s Estimate |
$176,948.20 |
| RK Sanders Inc. |
$139,869.00 |
| Eagle Mountain Construction, Inc |
$158,475.00 |
| Standard Construction Co. |
$190,001.00 |
| Woodruff Construction Co. |
$193,118.00 |
| RTR Paving and Resurfacing Inc. |
$221,005.00 |
After the City reviewed the bids, and had preliminary discussions with RK Sanders Inc., on March 12, 2013 RK Sanders officially withdrew their bid for consideration. The City accepted their request. The City is recommending award to the 2nd low responsive bidder, Eagle Mountain Construction, Inc. The 2nd low responsive bid amount is within budget and ADOT has endorsed the City’s recommendation.
Expanded Financial Considerations:
Community Benefits and Considerations:
Community Involvement:
Expanded Options and Alternatives:
- Approve the award as recommended.
- Reject the award and re-advertise the project. Rejecting could forfeit $79,237.50 in ADOT construction funding. The project would need to be suspended until alternate funding is found; or,
- Cancel the project and reprogram City matching funds for another project