- Meeting Date:
- 06/02/2015
- From:
- Steve Zimmerman, Parks Manager
Information
TITLE:
RECOMMENDED ACTION:
1) Approve the construction contract with TSG Constructors, LLC in the amount of $1,540,765.00 (which includes a $59,265 contract allowance) and a contract time of 120 calendar days;
2) Approve Change Order Authority to the City Manager in the amount of $122,160.00 (8% of the contract amount);
3) Authorize the City Manager to execute the necessary documents
Executive Summary:
Award of this contract will authorize the construction of the Bushmaster Park Improvements Project, 3150 N. Alta Vista Drive, in accordance with the approved park improvement plans prepared by The WLB Group, Inc. dated March 12, 2015. The project area is approximately 7 undeveloped acres located on the east side of Bushmaster Park.
The 1996 Parks & Recreation Bond allowed for the issuance of General Obligation Bonds for park improvements identified in the bond. Bed, Board and Booze (BBB) Recreation tax funds will also be used to support the construction.
Financial Impact:
The project has a total FY 15 budget appropriation in the BBB Recreation fund of $1,666,460. Of this, $1.1 million is provided through a General Obligation bond issuance and the remaining funds are provided from BBB Recreation. The General Obligation bond will be repaid through secondary property taxes as authorized by the voters in 1996.
Connection to Council Goal and/or Regional Plan:
3) Provide sustainable and equitable public facilities, services, and infrastructure systems in an efficient and effective manner to serve all population areas and demographic
REGIONAL PLAN:
Recreation
- Goal Rec.1. Maintain and grow the region's healthy system of convenient and accessible parks, recreation facilities, and trails.
Has There Been Previous Council Decision on This:
01-21-2014. Council approval of Ordinance 2014-03, Allowing for the sale of $1.1 M in General Obligation bonds to support this project.
01-28-2014 Council Work Session for presentation of Bushmaster Concept Design Report.
06-14-2014. Council adoption of the FY2015 Budget which included this project.
Options and Alternatives:
1) Approve the award as recommended. Approval will allow the work to move forward in calendar year 2015 or;
2) Reject approval of the award. This would delay the project. If rejection occurs, possible options include:
- Re-advertise the project and open new bids
- Suspend or cancel the project
Background/History:
These planned improvements are the direct result of a collaborative effort between various community groups and the City to address public safety and health concerns dating back to 2011. In 2012, an internal committee comprised of City staff from various departments was assembled by the City Manager to identify the stakeholders who would have a vested interest in the park and the underlying issues. With the coordinated effort and input from these stakeholders the Bushmaster Park Improvement Project was created.
The park improvements consists of constructing new parking areas, a new playground with ADA accessibility, a new amphitheater area with a large group ramada, a concrete roller rink, a new adult fitness area, a new restroom building, grading of all necessary retention and detention basins for the project, site lighting, and new landscaping. Access on the east side will be added with the construction of a new bridge over the Fanning Wash from N. Thomas Dr.
Staff solicited for construction bids on April 19 and April 26, 2015. Six bids were received by the opening date of April 30, 2015, and TSG Constructors were determined to be the lowest responsive responsible bidder. Staff determined to utilize a deductive alternative in the amount of $45,500 in order to include a change order amount of $59,265.00. A bid tabulation with the deductive alternate and change order amount is summarized below in the Expanded Financial Considerations.
Key Considerations:
-
Community Concerns
- Safety
- Accessibility
- Community Health
- New Facilities
- Dog Park
- Stormwater
Expanded Financial Considerations:
| Engineer's Estimate: $1,675,441.00 | ||||
| Contractor | Bid | Deductive Alt | Contract Allowance | Total |
| TSG Constructors | $ 1,527,000.00 | $ (45,500.00) | $ 59,265.00 | $ 1,540,765.00 |
| Woodruff | $ 1,599,099.50 | $ (45,500.00) | $ 59,265.00 | $ 1,612,864.50 |
| Eagle Mtn | $ 1,615,731.60 | $ (45,500.00) | $ 59,265.00 | $ 1,629,496.60 |
| Tri-Com Corp | $ 1,638,966.85 | $ (45,500.00) | $ 59,265.00 | $ 1,652,731.85 |
| Sky Construction | $ 2,190,242.06 | $ (45,500.00) | $ 59,265.00 | $ 2,204,007.06 |
| Capital Imp. | $ 2,468,000.00 | $ (45,500.00) | $ 59,265.00 | $ 2,481,765.00 |
Community Benefits and Considerations:
- Improved bridged access
- ADA accessible playground
- New restroom facilities
- New parking lots
- New ramada
- Roller rink
- Outdoor exercise area
Community Involvement:
The community has been informed and involved throughout this process through a series of public outreach meetings, public service announcements (PSA’s) and social media.
-
Community Outreach
- Public Outreach – March 27th, April 10th, May 15th, 2013
- PSA’s through newspaper & radio, City website, Recreation Services and SEMS Facebook and Bushmaster Community Block Watch website
- Concept plan posted on City website for comment period
- Final draft plan posted on city website and Bushmaster Community Block Watch website
Collaboration has involved many stakeholders from the community and city staff:
-
Community Partners
- Dr. Charles Hammersley, Professor, NAU, Parks & Recreation Management Program
- Lisa Jane Hardy, Ph.D. Research Assistant Professor, Department of Anthropology Fellow, Interdisciplinary Health Policy Institute, Northern Arizona University
- Bushmaster Community Block Watch Group
- North Country Healthcare
- Hermosa Vida – Change Action Network (C.A.N.)
- Coconino County Health District
- Parks & Recreation Commission