9.D.
City Council Meeting - FINAL
- Meeting Date:
- 11/15/2022
- Co-Submitter:
- Trevor Henry
- From:
- Jeremy DeGeyter, Project Manager
Information
TITLE:
Consideration and Approval of Contract: Approve Change Order No. 16 with Shephard Wesnitzer, Inc. in the amount of $151,200.00 and a 470 calendar day time extension for the Rio de Flag Flood Control Utility Relocation Design Services Contract.
STAFF RECOMMENDED ACTION:
- Approve Change Order No. 16 with Shephard Wesnitzer, Inc. the amount of $151,200.00 and a 470 calendar day time extension for the Rio de Flag Flood Control Utility Relocation Design Services Contract; and
- Authorize the City Manager to execute the necessary documents.
Executive Summary:
Approval of Change Order No. 16 will compensate Shephard Wesnitzer, Inc. (SWI) for assisting the City in acquiring the property rights necessary for the U.S. Army Corps of Engineers (USACE) to certify the real estate for construction based on the needed lands, easements, rights-of-way, relocations, and disposal site (LERRD) and complete design for the Rio de Flag Flood Control Project (Project). The additional tasks of Change Order No. 16 include coordinating the relocation of utilities within BNSF Railway (BNSF) right of way, provide additional legal descriptions for right of way and easement acquisitions, allow for the design for the replacement of the pedestrian bridge at City Hall, and the breakout and phasing of construction plans. There is a 470 calendar day time extension requested with Change Order No. 16 to ensure the estate necessary meets the guidelines and requirements as outlined by the USACE.
The Change Order Committee considered this item on October 27, 2022, it was approved with a recommendation to forward to the Council for final approval at the City Council meeting on November 15, 2022.
Change Order No. 16 is currently in routing for signatures to document approval of the Change Order Committee and will be attached to the final agenda for this item.
The Change Order Committee considered this item on October 27, 2022, it was approved with a recommendation to forward to the Council for final approval at the City Council meeting on November 15, 2022.
Change Order No. 16 is currently in routing for signatures to document approval of the Change Order Committee and will be attached to the final agenda for this item.
Financial Impact:
The FY 2004-2005 original Design Services Contract was approved by City Council to SWI in the amount of $1,582,521.00. Subsequent values of prior changes authorized through the City Manager’s Change Order Authority and City Council approval has resulted in an amount of $2,055,531.34. The funding to pay the amount of Change Order No. 16 ($151,200.00) will come from the Stormwater Fund, tracked in the Rio de Flag project account #206-08-385-3236-0-4421.
Original Contract Value $1,582,521.00
Value of Prior Changes $2,055,531.34
Value of this Change $ 151,200.00
New Contract Value $3,789,252.34
Original Contract Value $1,582,521.00
Value of Prior Changes $2,055,531.34
Value of this Change $ 151,200.00
New Contract Value $3,789,252.34
Policy Impact:
No Impact.
Connection to PBB Priorities/Objectives, Carbon Neutrality Plan & Regional Plan:
| Connection to PBB Priorities/Objectives, Carbon Neutrality Plan & Regional Plan: |
| Priority Based Budget Key Community Priorities and Objectives
|
Has There Been Previous Council Decision on This:
Previous City Council actions pertaining to authorized value changes and action items necessary for the continuation of the Project since FY 2004-2005.
Options and Alternatives:
- Approve Change Order No. 16 with SWI the amount of $151,200.00 and a 470 calendar day time extension as recommended; or
- Reject Change Order No. 16, which will forfeit the opportunity for the City to comply with its requirement to provide the estate necessary to allow the USACE to certify the real estate for the Rio de Flag Flood Control Project.
Background and History:
On January 18, 2005, the City Council awarded the Design Services Contract to SWI to perform design services for this Project.
Key Considerations:
| The Rio de Flag Flood Control Project is included in the City’s Stormwater Management Capital Improvement Program and is the number one priority. The Project has also been the subject of numerous City Council meetings, City-to-Citizen communications and newspaper articles. The USACE requested funding for their FY 20 work plan to construct the entire Project. The USACE received $52M which will complete their share (65%) of the project as outlined in the Project Cooperation Agreement. In 2018, the City Council authorized a fee increase to the Stormwater rate that would provide funding for the Capital Improvement Program (CIP). In 2019, City Council authorized collection of the rate increase. The rate increase will provide funding for the Stormwater CIP, of which the Rio de Flag Flood Control Project is the number one priority. The City has the capacity and commitment to complete our share of the project as outline in the Project Cooperation Agreement. On April 12, 2021, the USACE submitted to the City the real estate “take letter” outlining the estate necessary for the real estate certification. It is the City’s responsibility as outlined in the Project Cooperation Agreement to provide the corridor necessary for the USACE to solicit, award and construct the Project. A sample of the additional tasks contained in Change Order No. 16 includes: BNSF Utility Coordination:
Change Order No. 16 was presented to the Change Order Committee for their consideration on October 27, 2022. The item was approved with a recommendation to forward to the City Council for consideration and final approval. |
Community Benefits and Considerations:
| Funding for Change Order No. 16 ($151,200.00) will come from the Stormwater Fund and will be tracked in the Rio de Flag Flood Control project 206-08-385-3236-0-4421. The Stormwater Fee rate increase started collection in July 2019 to fund the Stormwater CIP. The Rio de Flag Flood Control Project is part of the Stormwater CIP and is the highest priority Project. The USACE was awarded $52M in their FY 20 work plan, providing commitment for their full share of the project at 65%. |