- Meeting Date:
- 06/04/2013
- Submitted For:
- Trevor Henry, Project Manager
- From:
- Trevor Henry, Project Manager
Information
TITLE:
RECOMMENDED ACTION:
1) Award the construction contract to LP’s Excavating, Inc. of Williams, Arizona in the total award amount of $1,741,893.15, which includes $80,000.00 in contract allowance. The contract period is 150 calendar days; and
2) Authorize Change Order Authority to the City Manager in the amount of $166,000.00 (10% of the bid contract amount, less contract allowance) for unanticipated additional costs; and
3) Authorize the City Manager to execute the necessary documents.
Policy Decision or Reason for Action:
Awarding the contract will authorize the construction of the La Plaza Vieja 2010 Bond Project in accordance with the approved public improvements as authorized by the Special Debt Authorization election of November 2010. Proceeding with the contract work will improve the La Plaza Vieja neighborhood, the project will comply with the 2010 Bond program including water, sewer and pavement resurfacing and reconstruction.
Financial Impact:
The La Plaza Vieja 2010 Bond Improvement project is funded by the total budget appropriation of $2,118,044 (includes FY 12 and FY 13 prior year expenditures) and FY 14 budget amount of $1,957,236 for the voter approved Street/Utility Bond Program (acct. 403-2437-691).
Connection to Council Goal:
Repair, Replace, and Maintain Infrastructure (Streets & Utilities)
Has There Been Previous Council Decision on This:
Yes, Council approval of the Special Debt Authorization Election held in November 2010 and authorizing general obligation bonds to fund Street and Utilities Improvements in a principle amount up to $16,500,000.
Options and Alternatives:
1) Approve the award as recommended.
2) Reject the approval of the award and direct staff to re-advertise the project. This option would delay the construction start date and cause the work to be deferred until 2014.
Background/History:
Construction impacts include traffic detours and temporary displacement of parking for the residents.
Key Considerations:
Expanded Financial Considerations:
Community Benefits and Considerations:
Community Involvement:
Expanded Options and Alternatives:
- Approve the award as recommended.
- Reject approval of the award. This option would delay the construction start and cause the work to be deferred until 2014. Provide additional direction to staff.