Agenda Item # 9.i.
City Commission Regular Meeting
- Meeting Date:
- 03/02/2015
- Re
- Change Order No. 1 to Bellingham Marine in the Amount of $11,832.60
- Submitted For:
- John Andrews
SUBJECT:
Approval of Change Order No. 1 to Bellingham Marine in the amount of $11,832.60 to change the Marina electrical pedestal breakers from standard breakers to a 30 milliampere instantaneous trip breaker pending approval by the City Attorney.
SUMMARY:
A change to the national electrical code and a requirement of the City’s electrical specification has created a condition (nuisance tripping) that marinas have not had to deal with in the past. The system that was provided by the electrical equipment manufacture meets the requirements of the 2011 National Electric Code and the manufactures requirements to receive a UL listing for its products and the City’s specifications. This change will allow the electrical system to meet all of the code and specification requirements while allowing for an isolated shut down of an individual pedestal versus shutting down the main electrical Substation to the individual dock under a ground fault current that exceeds 30 milliampere.This change will also reduce the amount of nuisance tripping of the main Substation panels caused by excessive ground fault current leakage.
RECOMMENDATION:
Approval
ALTERNATIVES:
N/A
RESPONSIBLE STAFF:
Edward Seissiger, Engineering Project Coordinator
COORDINATED WITH:
Kevin Thompson, Bellingham Marine and Bob Dively, Marina Electrical Equipment
Fiscal Impact
- Budgeted Y/N:
- N
- Fiscal Year:
- 2014-15
- Account:
- 401-4100-575-6360
- Amount:
- 11,832.60
FISCAL IMPACT:
This is a non budgeted item. We will try to have this item reimbursed by FEMA during project close out. FEMA may consider this an upgrade which will not be eligible for reimbursement.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Finance Department | gjohnson | 02/19/2015 11:29 AM |
| City Manager | rbradshaw | 02/25/2015 02:35 PM |
- Form Started By:
- eseissiger
- Started On:
- 02/18/2015 01:26 PM
- Final Approval Date:
- 02/25/2015