SUMMARY:

The engineering plans have been completed and all construction permits have been obtained.  The following timeline identifies the project's key events:
1. Advertisement for construction bids - 2/23/15 and 3/2/15
2. Mandatory pre-bid meeting - 3/12/15 
3. Bid opening - 3/23/15
4. Commission approval of contract award - 4/6/15
5. Contract execution and issuance of Notice to Proceed - 5/6/15
6. Substantial construction completion - 9/3/15
7. Final construction completion - 10/3/15

RECOMMENDATION:

N/A

ALTERNATIVES:

N/A

RESPONSIBLE STAFF:

Engineering

COORDINATED WITH:

FPRA
Public Works
 

Fiscal Impact

Budgeted Y/N:
N/A
Fiscal Year:
N/A
Account:
N/A
Amount:
N/A

OTHER INFORMATION:

Funding for this $625,000 project was previously approved by Florida Inland Navigational District Assistance Program in the amount of $312,500 and with a 50% match being provided by the City of Fort Pierce Parks MSTU and Park Impact Fees in the amount of $312,500.

Attachments

Form Review

Inbox Reviewed By Date
City Manager rbradshaw 02/25/2015 02:36 PM
Form Started By:
Tracy Telle
Started On:
02/19/2015 12:45 PM
Final Approval Date:
02/25/2015