Agenda Item # 11.c.
City Commission Regular Meeting - 4:30 pm
Meeting Date:
05/17/2021
Re
Bid No. 2019-024 - Change Order No. 1 - N. 17th St. Roadway Improvements - Pav-Co Contracting, Inc.
Submitted For:
John Andrews

SUBJECT:

Approval of North 17th Street Roadway Improvements Change Order No. 1 in the total amount of $211,431.88.

SUMMARY:

This change order includes compensation for additional work on the North 17th Street Roadway Improvements. Changes include addition of drainage structures and pipes, paver crosswalks, conduit installation and a 10-inch forcemain. Changes also includes the removal of trees, an existing underground drainage structure and pipe. 

RECOMMENDATION:

Staff recommends approval

ALTERNATIVES:

Staff shall proceed as directed by the City Commission

RESPONSIBLE STAFF:

Engineering Department

COORDINATED WITH:

Engineering Department
Pav-CO Contracting, Inc - Contractor
Captec Engineering, Inc. - CEI Services

Fiscal Impact

Budgeted Y/N:
Y
Fiscal Year:
FY20/21
Account:
See Below
Amount:
211,431.88

FISCAL IMPACT:

Funding shall be encumbered from the following

1. Roads and Bridges Impact Fees - Account No. 114-1111-519-6310 in the amount of $62,525.00
2. SUR Expense - Account No. 114-1111-519-6321 in the amount of $32,029.79
3. SMU Revenue - Account No. 403-4300-530-6330 in the amount of $116,877.09 with FPUA reimbursement in the amount of $102,400.05

Attachments

Form Review

Inbox Reviewed By Date
Finance Department Johnna Morris 05/11/2021 05:03 PM
City Manager Nick Mimms 05/12/2021 03:54 PM
Form Started By:
Venetia Barnes
Started On:
04/30/2021 03:54 PM
Final Approval Date:
05/12/2021