8.e.
FPRA Regular Meeting
- Meeting Date:
- 11/14/2023
- Re
- General Contractor Services Agreement for the Exterior Restoration of Old St. Anastasia, Bid No. 2023-037, for the Amount of $588,168.46
- Submitted For:
- Shyanne Harnage
SUBJECT:
General Contractor Services Agreement for the Exterior Restoration of Old St. Anastasia, Bid No. 2023-037, for the Amount of $588,168.46.
SUMMARY:
On August 8, 2023, the Fort Pierce Redevelopment Agency (FPRA) Board awarded Request for Proposals, Bid Number 2023-037, to Innovative Masonry Restoration, LLC, for the exterior restoration of the Old St. Anastasia Catholic School Building. The Board directed staff to enter contract negotiation with the awardee. The FPRA has budgeted $500,000 for the exterior restoration as part of a multi-phased approach toward the redevelopment of the site. City staff is recommending an increased budget at a total of $588,168.46, which is based upon negotiation with the awardee.
The exterior restoration of Old St. Anastasia will help achieve the FPRA’s goal to eliminate slum and blight and support historic preservation and cultural heritage activities within the redevelopment area.
The exterior restoration of Old St. Anastasia will help achieve the FPRA’s goal to eliminate slum and blight and support historic preservation and cultural heritage activities within the redevelopment area.
RECOMMENDATION:
Staff recommends approval of the agreement.
ALTERNATIVES:
Staff will proceed as directed by the FPRA Board
RESPONSIBLE STAFF:
Marsha Commond, Redevelopment Specialist
COORDINATED WITH:
Nick Mimms, City Manager
Shyanne Harnage, Economic Development Manager
Shyanne Harnage, Economic Development Manager
Fiscal Impact
- Budgeted Y/N:
- Y
- Fiscal Year:
- 23-24
- Account:
- 1049400-562100
- Amount:
- $588,168.46
OTHER INFORMATION:
N/A