Avenue B Construction Change Order No. 1 - Heavy Civil Bid No 2022-016
Submitted For:
Selena Griffett

SUBJECT:

Approve Avenue B Construction Change Order No 1 for Heavy Civil, Inc., Bid No. 2022-016 in the amount of $7,548.96.

SUMMARY:

During construction of the improvements to Avenue B from 13th Street to 8th Street, there were changes and field directives that were authorized using contingency funding. A summary of the changes and field directives is attached in the Change Order No 1 document. Additionally, there were item cost overruns and underruns that were applied throughout construction. These are also detailed in the attached Change Order No 1 document.

Construction by Heavy Civil Inc. is complete as of November 15, 2023.  Under grounding of overhead utilities is ongoing, but the roadway is open to traffic. 

The final invoice has been submitted for payment with the retainage payment due. Staff has reconciled all Heavy Civil costs and has determined that a Change Order in the amount of $7,548.96 is needed to close the construction contract. 

RECOMMENDATION:

Approve Change Order No.1 in the amount of $7,548.96.

ALTERNATIVES:

Renegotiate final contract amount.

RESPONSIBLE STAFF:

Selena Griffett

COORDINATED WITH:

City Engineer
City Attorney

Fiscal Impact

Budgeted Y/N:
N
Fiscal Year:
2024
Account:
114-1111-519-6310
Amount:
7,548.96

FISCAL IMPACT:

Funds to be allocated from Infrastructure Surtax

Attachments

Form Review

Inbox Reviewed By Date
Finance Department Johnna Morris 01/04/2024 10:41 AM
City Manager Nick Mimms 01/04/2024 10:48 AM
Form Started By:
Selena Griffett
Started On:
12/11/2023 11:08 AM
Final Approval Date:
01/04/2024