Agenda Item # 8.a.
City Commission Budget Workshop - 9:00 a.m.
Meeting Date:
07/08/2024
Re
Approval of Heavy CO No. 2 - Avenue B Roadway Reconstruction - Ref. Bid No. 2022-016
Submitted For:
Selena Griffett

SUBJECT:

Approval of Heavy Civil, Inc. Change Order 2 in the amount of $16,392.50 for final sidewalk construction along the Avenue B (8th Street to 13th Street) Roadway Reconstruction project.
 

SUMMARY:

The Avenue B Reconstruction project from 8th Street to 13th Street was substantially completed in November 2023. The City Commission approved Change Order 1 during the January 16, 2024, meeting which included the reconciliation of construction costs. 

This change order includes compensation for the construction of 185 square yards of concrete sidewalk which remains to be completed due to the delay of outside utility agencies completing their relocation of their overhead facilities to underground.

RECOMMENDATION:

Staff recommends approval of Change Order 2.

ALTERNATIVES:

An alternative is to direct staff to receive bids from other contractors. 

RESPONSIBLE STAFF:

Selena Griffett

COORDINATED WITH:

John Andrews
City Attorney
Contractor (Heavy Civil, Inc)

Fiscal Impact

Budgeted Y/N:
N/A
Fiscal Year:
2024
Account:
1141111-563210
Amount:
$16,392.50

FISCAL IMPACT:

Funding is available from the Infrastructure Surtax Account No. 1141111-563210.

Attachments

Form Review

Inbox Reviewed By Date
Finance Department Johnna Morris 06/24/2024 01:59 PM
City Manager Nick Mimms 06/24/2024 04:14 PM
Form Started By:
Selena Griffett
Started On:
06/20/2024 01:02 PM
Final Approval Date:
06/24/2024