Approval of Change Order No. 11 Journey C & D Group, Inc.
Submitted For:
Audria Moore

SUBJECT:

Approval of Change Order No. 11 to General Contractor Services-Highway Museum in an amount not to exceed $2,803.70 for the City of Fort Pierce Florida Highwaymen Museum renovation project.

SUMMARY:

The proposed change order aims to enhance security and provide additional protection to minimize the risk of theft of the newly installed HVAC units.

RECOMMENDATION:

Staff recommends approval of Changer Order No. 11 to General Contractor Services-Highway Museum in an amount not to exceed $2,803.70 to supply and install 2 security cages for the HVAC units. 

ALTERNATIVES:

Staff will proceed as directed by the FPRA Board.

RESPONSIBLE STAFF:

Audria V. Moore, Special Projects Coordinator

COORDINATED WITH:

Richard Stauffer, Facilities Manager
Journey C&D Group, Inc.

Fiscal Impact

Budgeted Y/N:
Y
Fiscal Year:
2025
Account:
104-9400-554-000-000
Amount:
$2,803.70

OTHER INFORMATION:

The change order not to exceed $2,803.70 will be funded by FPRA Account Number: Improvements – Other Improvements - #104-9400563200.