Skip to main content

AgendaQuick™

View Agenda Item

7.B.
Special Magistrate Hearing - Building
Meeting Date:
12/12/2024

Information

SUBJECT:

 23-2183  3220 S US Hwy 1 Units 6 - 8  Commonwealth Multi-Properties  Shaun Coss

CASE INFORMATION:

 Case Initiated:  July 27, 2023  Type of Presentation:  Fine Reduction 

OWNER:

OWNER:
 Commonwealth Multi-properties
 16370 NW 8th Dr
 Pembroke Pines FL 33028
REG. AGENT:
 Malkit Singh Sappal

 

VIOLATIONS:

FBC 105.1 (2020) Permit Required

REDUCTION CRITERIA:
1. THE GRAVITY OR SERIOUSNESS OF THE VIOLATION:  Moderate.

2. ANY AND ALL ACTIONS TAKEN BY THE VIOLATOR TO CORRECT THE VIOLATIONS(S); OR IF THE VIOLATION(S) WERE NOT CORRECTED BY THE ORIGINAL VIOLATOR, WHAT ACTION WAS TAKEN BY ANY OTHER OWNER OR PARTY IN THE INTEREST TO BRING THE VIOLATION INTO COMPLIANCE? A permit for the remodel of the 3 suites was issued 10 months after the initiation of the case.  The work has been completed, inspected and a Certificate of Occupancy has been issued.

3.  THE NUMBER OF TIMES THE VIOLATOR WAS PREVIOUSLY FOUND IN VIOLATION BY EITHER THE CODE ENFORCEMENT BOARD, SPECIAL MAGISTRATE, OR OTHER QUASI-JUDICIAL OR JUDICIAL PROCESS, OR OTHERWISE ADMITTED GUILT IN ANY SUCH PROCEEDING?   4 (four).

FINDINGS/ORDER:

Order Determining Violation - November 15, 2023
Affidavit of Non-Compliance - February 22, 2024
Order Approving Respondent's Request For Extension of Time - April 12, 2024
Affidavit of Compliance - September 20, 2024

ACTION DATES:

1. November 15, 2023 - Special Magistrate Hearing - the owner was provided 60 days to get a permit or fines may accrue.
2. February 22, 2024 - An Affidavit of Non-Compliance was prepared and recorded on February 23, 2024.  Fines began on February 22, 2024.
3. March 13, 2024 - An email was received contesting the fines.
4. March18, 2024 - A Massey Hearing Notice was mailed.
5. April 4, 2024 - A DPCR application was received and approved on the same day.  The contractor was emailed and informed of this approval allowing for the building permit to be applied for.
6. April 11, 2024 - Special Magistrate Hearing requesting an extension of time and staying of the fines was approved providing a 90 day extension to get the necessary permit. The accumulated fines total $4,940.00, including $40.00 in recording fees.
7. May 23, 2024 - The permit was issued.  On July 25, 2024 the Final Building inspection was approved complying this case. An Amended Affidavit of Compliance was recorded on December 4, 2024.
8. October 22, 2024 - A request for the Reduction of the Fines was received.
9. November 5, 2024 - A Hearing Notice was sent.

 

RECOMMENDATION:

To be determined.

Attachments

Form Review

Form Started By:
Elizabeth Beck
Started On:
12/04/2024 12:47 PM
Final Approval Date:
12/05/2024