8.
FPRA Regular Meeting Agenda
Meeting Date:
01/21/2014
Re
King Plant Site Redevelopment RFQ/RFP
Submitted For:
Nick Mimms

Information

SUBJECT:

Update on King Plant Development RFQ/RFP - Deputy City Manager

SUMMARY:

Urban Redevelopment Department Staff has developed the specific parameters of the two phased request for qualifications/proposals which corresponds to the adopted Community Redevelopment Agency Plan. The schedule is as follows:

Notification to newspaper:  January 13, 2014
Publishing dates:  January 22 & 29, 2014
Pre-Proposal Meeting:  February 6, 2014
Last day questions:  February 24, 2014
(7 working days prior to the due date/opening)
Due date (opening):  March 5, 2014
(30 working days after the first advertisement)

RECOMMENDATION:

Staff recommends the acceptance of the proposed RFQ/RFP schedule.

ALTERNATIVES:

Do not accept schedule.

RESPONSIBLE STAFF:

Administrative Services Department / Procurement Division

COORDINATED WITH:

Urban Redevelopment Department

Fiscal Impact

Budgeted Y/N:
Fiscal Year:
Account:
Amount:

OTHER INFORMATION:

None