8.
FPRA Regular Meeting Agenda
- Meeting Date:
- 01/21/2014
- Re
- King Plant Site Redevelopment RFQ/RFP
- Submitted For:
- Nick Mimms
Information
SUBJECT:
Update on King Plant Development RFQ/RFP - Deputy City Manager
SUMMARY:
Urban Redevelopment Department Staff has developed the specific parameters of the two phased request for qualifications/proposals which corresponds to the adopted Community Redevelopment Agency Plan. The schedule is as follows:
Notification to newspaper: January 13, 2014
Publishing dates: January 22 & 29, 2014
Pre-Proposal Meeting: February 6, 2014
Last day questions: February 24, 2014
(7 working days prior to the due date/opening)
Due date (opening): March 5, 2014
(30 working days after the first advertisement)
Notification to newspaper: January 13, 2014
Publishing dates: January 22 & 29, 2014
Pre-Proposal Meeting: February 6, 2014
Last day questions: February 24, 2014
(7 working days prior to the due date/opening)
Due date (opening): March 5, 2014
(30 working days after the first advertisement)
RECOMMENDATION:
Staff recommends the acceptance of the proposed RFQ/RFP schedule.
ALTERNATIVES:
Do not accept schedule.
RESPONSIBLE STAFF:
Administrative Services Department / Procurement Division
COORDINATED WITH:
Urban Redevelopment Department
Fiscal Impact
- Budgeted Y/N:
- Fiscal Year:
- Account:
- Amount:
OTHER INFORMATION:
None
- Budgeted Y/N: