6.k.
Planning Board
- Meeting Date:
- 05/08/2018
Information
REQUESTED ACTION
Development Review & Design Review - Bev Smith Toyota - 3350 S. US Highway 1
LOCATION
3350 S. US Hwy 1
RESPONSIBLE STAFF
Brandon C. Creagan, LEED Green Associate, Planner
RECOMMENDATION
The requested Applications for Development Review & Design Review meet the requirements of the City Code and are found to be consistent with the City’s Comprehensive Plan; therefore Staff recommends that the Planning Board forward a recommendation of approval to the City Commission with the following conditions:
1.Coordinate with St. Lucie County for the installation of sidewalks along Dixieland Drive and Southland Drive.
2.Schedule a meeting with Planning Staff and the City Arborist to discuss the proposed tree mitigation that was discussed at the project intake meeting. Please schedule this meeting prior to the City Commission meeting.
3.Before a CO is issued, please provide a landscape bond for all proposed landscaping pursuant to City Code 22-180.
4.A Unity of Title will be needed prior to the issuance of a Building Permit.
5. Please provide a copy of the approved agreement made with the County that grants approval to move Southland Drive to the new desired location. This agreement must be submitted with the Building Permit.
1.Coordinate with St. Lucie County for the installation of sidewalks along Dixieland Drive and Southland Drive.
2.Schedule a meeting with Planning Staff and the City Arborist to discuss the proposed tree mitigation that was discussed at the project intake meeting. Please schedule this meeting prior to the City Commission meeting.
3.Before a CO is issued, please provide a landscape bond for all proposed landscaping pursuant to City Code 22-180.
4.A Unity of Title will be needed prior to the issuance of a Building Permit.
5. Please provide a copy of the approved agreement made with the County that grants approval to move Southland Drive to the new desired location. This agreement must be submitted with the Building Permit.
Attachments
- Planning Staff Report
- Applications
- Site Plan
- Environmental Assessment
- Traffic Analysis
- TRC Comments
- TRC Comment Response from Applicant
Form Review
- Form Started By:
- bcreagan
- Started On:
- 05/02/2018 02:35 PM
- Final Approval Date: