Agenda Item # 13.a.
City Commission Regular Meeting
Meeting Date:
01/22/2019
Re
FDOT Joint Participation Agreement (JPA) Amendment No. 2 - Ohio Avenue and US Highway 1 Intersection Improvements
Submitted For:
John Andrews

SUBJECT:

Resolution 19-R03 authorizing the execution of FDOT's JPA Amendment No. 2 which provides additional project funding in the amount of $100,000.

SUMMARY:

The original JPA provided project funding in the amount of $150,000 to compensate for construction costs associated with the proposed intersection improvements to Ohio Avenue and US 1.  These improvements include the realignment of the skewed east-west legs of the intersection, installation of three (3) mast arms complete with associated traffic signal equipment.  The total State project reimbursement of $250,000 towards the estimated $506,000 intersection construction cost is proposed.  This does not include the cost of the proposed improvements to Ohio Avenue between US 1 and 3rd Street which is estimated at $509,000.

RECOMMENDATION:

Staff recommends approval

ALTERNATIVES:

Deny and leave intersection as is

RESPONSIBLE STAFF:

Engineering

COORDINATED WITH:

FDOT

Fiscal Impact

Budgeted Y/N:
N
Fiscal Year:
FY 19/20
Account:
TBD
Amount:
$505,741.40

FISCAL IMPACT:

Total intersection construction cost of $505,741.40 will have a $250,000 reimbursement by the State leaving $255,741.40 to be compensated by the City.

Attachments

Form Review

Inbox Reviewed By Date
Finance Department Johnna Morris 01/14/2019 05:24 PM
City Manager Nick Mimms 01/16/2019 12:56 PM
Form Started By:
Tracy Telle
Started On:
01/02/2019 08:20 AM
Final Approval Date:
01/16/2019