Agenda Item # 9.f.
City Commission Regular Meeting
Meeting Date:
05/19/2014
Re
Park Trail Acres Drainage Improvements - Johnson-Davis, Inc. CO No. 1
Submitted For:
John Andrews

SUBJECT:

Approval of Johnson and Davis's Change Order No. 1 in the amount of $164,237.27 for additional construction services required to finalize the Park Trails Drainage Improvement Project.  

SUMMARY:

Request approval of Johnson and Davis's Change Order No. 1 in the amount of $164,237.27.  Additional construction services, as detailed on the attached change order, were required in order to finalize the Park Trails Drainage Improvement Project.

RECOMMENDATION:

Staff recommends approval.

ALTERNATIVES:

Advertise for bids.

RESPONSIBLE STAFF:

Engineering

COORDINATED WITH:

Public Works

Fiscal Impact

Budgeted Y/N:
N/A
Fiscal Year:
N/A
Account:
403-4300-538-3490
Amount:
$164,237.27

FISCAL IMPACT:

The additional work will be encumbered from the Stormwater Management Utility Fund, Account No. 403-4300-538-3490, in the amount of $164,237.27. Reference Purchase Order No. 14-0432, Bid No. 2013-003, Project No. SMUPTA