Agenda Item # 11.k.
City Commission Regular Meeting
- Meeting Date:
- 12/03/2018
- Re
- Contractual Agreement for Lincoln Park Main Street
- Submitted For:
- Libby Woodruff
SUBJECT:
Approve Contractual Agreement for Lincoln Park Main Street to recieve funding through Community Development Block Grant funds as approved in the 2018-2019 CDBG Action Plan in the total amount of $50,000.
SUMMARY:
2018-2019 CDBG Action Plan included funding Lincoln Park Main Street as they serve as the Community Based Development Organization (CBDO). This agenda item is for the approval of the Commission of the CBDO contractual agreement for the 2018-2019 program year.
RECOMMENDATION:
Approve the contractual agreement for Lincoln Park Main Street.
ALTERNATIVES:
Do not approve the contractual agreement.
RESPONSIBLE STAFF:
Caleta Scott, Lincoln Park Revitalization Coordinator
Libby Woodruff, Grants Administration Manager
Libby Woodruff, Grants Administration Manager
COORDINATED WITH:
Johnna Morris, Director of Finance
Fiscal Impact
- Budgeted Y/N:
- Y
- Fiscal Year:
- 2018
- Account:
- 10390025548230
- Amount:
- 50000
FISCAL IMPACT:
This expenditure will be reimbursed to the City via 2018-2019 CDBG.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Finance Department | Karen Logue | 11/16/2018 02:01 PM |
| Finance Department | Karen Logue | 11/26/2018 10:29 AM |
| City Manager | Nick Mimms | 11/27/2018 02:51 PM |
- Form Started By:
- cscott
- Started On:
- 11/13/2018 01:48 PM
- Final Approval Date:
- 11/27/2018