Agenda Item # 11.c.
City Commission Regular Meeting
Meeting Date:
04/15/2019
Re
Ohio Avenue Improvements CEI Services - Culpepper & Terpening SA No. 4 (RFQ 2013-005)
Submitted For:
John Andrews

SUBJECT:

Approval of Specific Authorization No. 4 in an amount not to exceed $86,414.00 for construction engineering inspection (CEI) services relating to the Ohio Avenue Roadway Improvements construction project.

SUMMARY:

The proposed construction includes the realignment of the roadway, east of U.S. Highway 1 to South 3rd Street, in order to better align the eastern leg with the west leg of Ohio Avenue.  The proposed improvements include signalization, drainage improvements, curb & gutter, sidewalks, landscape, and irrigation.  The City is required to retain an FDOT certified CEI consultant to oversee construction activities and provide verification testing as needed.

RECOMMENDATION:

Staff recommends approval

ALTERNATIVES:

Negotiate with another continuing service provider on the City's professional consultant list.

RESPONSIBLE STAFF:

Engineering

COORDINATED WITH:

FDOT

Fiscal Impact

Budgeted Y/N:
N
Fiscal Year:
N /A
Account:
10011115196310
Amount:
$86,414.00

FISCAL IMPACT:

The $86,414.00 shall be encumbered from the Road and Bridges Impact Fee Revenue Account.

Attachments

Form Review

Inbox Reviewed By Date
Finance Department Johnna Morris 04/10/2019 09:34 AM
City Manager Nick Mimms 04/10/2019 10:30 AM
Form Started By:
Tracy Telle
Started On:
04/02/2019 09:21 AM
Final Approval Date:
04/10/2019