Approval of Change Order No. 7 to CW Roberts Contracting Inc.
Submitted For:
John Andrews

SUBJECT:

Request approval of Change Order No. 7 to CW Roberts Contracting Inc. in the amount of $90,490.28 for the Surfside neighborhood drainage improvements.

SUMMARY:

This change order is requested to cover items not included in the original bid, such as replacement of decorative driveways,  repair work of failed underground piping discovered during construction, and additional grading and sod to make right of way tie-ins to existing property elevations..  

RECOMMENDATION:

Recommend approval of this change order

ALTERNATIVES:

Proceed as directed by the City Commission

RESPONSIBLE STAFF:

Edward Seissiger, Project Manager

COORDINATED WITH:

Ben Baummier, Project Manager CW Roberts Contracting

Fiscal Impact

Budgeted Y/N:
N
Fiscal Year:
2018/19
Account:
403-4300-538-3490
Amount:
90,490.28

FISCAL IMPACT:

This Change order will be funded from the City's SMU account

Attachments

Form Review

Inbox Reviewed By Date
Finance Department Johnna Morris 10/02/2019 10:02 AM
City Manager Nick Mimms 10/02/2019 11:50 AM
Form Started By:
eseissiger
Started On:
09/23/2019 10:17 AM
Final Approval Date:
10/02/2019