Furnish and Install Asphaltic Concrete - 2018 Street Resurfacing - Change Order 9
Submitted For:
John Andrews

SUBJECT:

Approval of Change Order No. 9 with CW Roberts Contracting for the final closeout of contract for Avenue A and Avenue B Reconstruction in the total amount of $14,005.33.

SUMMARY:

This is a request for the approval of Change Order No. 9 to the master contract with CW Roberts Contracting, Inc. to Furnish and Install Asphaltic Concrete - 2018 Street Resurfacing.  Change Order No. 9, includes compensation for completion of the reconstruction of Avenue A and Avenue B between 7th and 8th Streets.  This is the closeout for this project, adjusting quantities for the overrun and underruns of specific items needed to complete the project.

RECOMMENDATION:

Engineering recommends approval of the Change Order

ALTERNATIVES:

Renegotiate final change order

RESPONSIBLE STAFF:

Jack Andrews, City Engineer

COORDINATED WITH:

Fort Pierce Utilities Authority

Fiscal Impact

Budgeted Y/N:
N
Fiscal Year:
N/A
Account:
N/A
Amount:
14005.33

FISCAL IMPACT:

This change order will be funded from the Half-cent Surtax Account in the amount of $14,005.33.

Attachments

Form Review

Inbox Reviewed By Date
Finance Department Johnna Morris 03/04/2020 11:38 AM
City Manager Nick Mimms 03/05/2020 01:57 PM
Form Started By:
jandrews
Started On:
02/26/2020 02:25 PM
Final Approval Date:
03/05/2020