Agenda Item # 11.a.
City Commission Regular Meeting
- Meeting Date:
- 02/03/2020
- Re
- Approval of RFP No. 2018-004 Change Order No. 3 to Gator Dredging for ICWW Dredging
- Submitted For:
- John Andrews
SUBJECT:
Approval of RFP No. 2018-004 Change Order No. 3 to Gator Dredging for the Intra-Coastal Water Way dredging in the amount of $523,900.00.
SUMMARY:
Approval of Change Order No. 3 to Waterfront Properties Services, LLC dba Gator Dredging in the amount of $523,900.00. This is to remove approximately 7500 Cu. yds of spoil material from the Intra Coastal Water Way (ICWW) channel prior to the start of turtle nesting season per the request of the Army Corps of Engineers. Pending final approval of the City Attorney as to form and correctness.
RECOMMENDATION:
Approval
ALTERNATIVES:
Seek alternative bids and/or wait to start the project after turtle nesting season next year.
RESPONSIBLE STAFF:
Ed Seissiger, Engineering Project Manager
COORDINATED WITH:
Bret Sap, Project Superintendent Gator Dredging
Fiscal Impact
- Budgeted Y/N:
- N
- Fiscal Year:
- 2019/2020
- Account:
- 401-4100-575-63-20
- Amount:
- $523,900.00
FISCAL IMPACT:
This is a non budgeted item, Army Corps of Engineers has requested it to be completed prior to the start of turtle nesting season.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Finance Department | Johnna Morris | 01/27/2020 10:24 AM |
| City Manager | Nick Mimms | 01/28/2020 08:32 AM |
- Form Started By:
- eseissiger
- Started On:
- 01/14/2020 09:35 AM
- Final Approval Date:
- 01/28/2020