Request approval for FPUA installation of street lights for North 17th Street Roadway Project
Submitted For:
John Andrews

SUBJECT:

Approval for FPUA to provide and install decorative street lights on the North 17th Street Roadway Improvement project in the amount of $125,130.00.

SUMMARY:

As a part of the North 17th Street Roadway Improvement project, FPUA will underground the electrical power lines. The power poles will be removed. Thirty-five (35) decorative LED light fixtures and poles will be installed along the corridor from Orange Avenue to Avenue D.  FPUA will provide the materials and install the street lights.

RECOMMENDATION:

Staff recommends approval

ALTERNATIVES:

Change order to the North 17th Street Roadway contract to have the contractor purchase and install the city street lights at a higher cost.

RESPONSIBLE STAFF:

Engineering

COORDINATED WITH:

FPUA

Fiscal Impact

Budgeted Y/N:
Y
Fiscal Year:
2020
Account:
100-1111-519-6310
Amount:
125,130

FISCAL IMPACT:

The $125,130.00 will be from the Road and Bridges Impact Fee Revenue Account

Attachments

Form Review

Inbox Reviewed By Date
Finance Department Gelencia Carter 05/21/2020 09:10 AM
City Manager Nick Mimms 05/26/2020 06:52 PM
Form Started By:
Venetia Barnes
Started On:
05/20/2020 03:31 PM
Final Approval Date:
05/26/2020