Agenda Item # 11.a.
City Commission Regular Meeting
- Meeting Date:
- 03/02/2015
- Re
- Melody Lane Fishing Pier Project Update
- Submitted For:
- John Andrews
SUBJECT:
Melody Lane Fishing Pier Update
SUMMARY:
The engineering plans have been completed and all construction permits have been obtained. The following timeline identifies the project's key events:
1. Advertisement for construction bids - 2/23/15 and 3/2/15
2. Mandatory pre-bid meeting - 3/12/15
3. Bid opening - 3/23/15
4. Commission approval of contract award - 4/6/15
5. Contract execution and issuance of Notice to Proceed - 5/6/15
6. Substantial construction completion - 9/3/15
7. Final construction completion - 10/3/15
1. Advertisement for construction bids - 2/23/15 and 3/2/15
2. Mandatory pre-bid meeting - 3/12/15
3. Bid opening - 3/23/15
4. Commission approval of contract award - 4/6/15
5. Contract execution and issuance of Notice to Proceed - 5/6/15
6. Substantial construction completion - 9/3/15
7. Final construction completion - 10/3/15
RECOMMENDATION:
N/A
ALTERNATIVES:
N/A
RESPONSIBLE STAFF:
Engineering
COORDINATED WITH:
FPRA
Public Works
Public Works
Fiscal Impact
- Budgeted Y/N:
- N/A
- Fiscal Year:
- N/A
- Account:
- N/A
- Amount:
- N/A
OTHER INFORMATION:
Funding for this $625,000 project was previously approved by Florida Inland Navigational District Assistance Program in the amount of $312,500 and with a 50% match being provided by the City of Fort Pierce Parks MSTU and Park Impact Fees in the amount of $312,500.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| City Manager | rbradshaw | 02/25/2015 02:36 PM |
- Form Started By:
- Tracy Telle
- Started On:
- 02/19/2015 12:45 PM
- Final Approval Date:
- 02/25/2015