Agenda Item # 9.j.
City Commission Regular Meeting
Meeting Date:
03/02/2015
Re
Change Order No.2 to Bellingham Marine in the Amount of $31,366.50
Submitted For:
John Andrews

SUBJECT:

Approval of Change Order No.2 to Bellingham Marine in the amount of $31,366.50 for the replacement of 6 wood navigational markers with steel marker poles in the deeper water of the City Marina entrance channel pending approval by City Attorney.   

SUMMARY:

The Marina has been requested by the Coast Guard to realign and renumber the Marina's entrance channel. The Marina also expends annually approximately $10,000.00 replacing wood navigational markers due to boat impacts. The wood markers tend to shear at the mud line making them unusable, switching to the steel pile will help reduce the annual cost to maintain the markers.

RECOMMENDATION:

Approval

ALTERNATIVES:

Continue to utilize the wood markers and complete the realignment and renumbering requested by the Coast Guard.

RESPONSIBLE STAFF:

Ed Seissiger, Engineering Project Coordinator

COORDINATED WITH:

Dean Kubitschek, Marina Manager and Coast Guard and Kevin Thompson, Bellingham Marine

Fiscal Impact

Budgeted Y/N:
N
Fiscal Year:
2014/15
Account:
401-4100-575-64-45
Amount:
31,366.50

FISCAL IMPACT:

This will be a capital expenditure.

Attachments

Form Review

Inbox Reviewed By Date
Finance Department gjohnson 02/19/2015 11:29 AM
City Manager rbradshaw 02/25/2015 02:36 PM
Form Started By:
eseissiger
Started On:
02/18/2015 03:48 PM
Final Approval Date:
02/25/2015