Agenda Item # 11.b.
City Commission Regular Meeting - 5:05 pm
- Meeting Date:
- 01/16/2024
- Re
- Avenue B Construction Change Order No. 1 - Heavy Civil Bid No 2022-016
- Submitted For:
- Selena Griffett
SUBJECT:
Approve Avenue B Construction Change Order No 1 for Heavy Civil, Inc., Bid No. 2022-016 in the amount of $7,548.96.
SUMMARY:
During construction of the improvements to Avenue B from 13th Street to 8th Street, there were changes and field directives that were authorized using contingency funding. A summary of the changes and field directives is attached in the Change Order No 1 document. Additionally, there were item cost overruns and underruns that were applied throughout construction. These are also detailed in the attached Change Order No 1 document.
Construction by Heavy Civil Inc. is complete as of November 15, 2023. Under grounding of overhead utilities is ongoing, but the roadway is open to traffic.
The final invoice has been submitted for payment with the retainage payment due. Staff has reconciled all Heavy Civil costs and has determined that a Change Order in the amount of $7,548.96 is needed to close the construction contract.
Construction by Heavy Civil Inc. is complete as of November 15, 2023. Under grounding of overhead utilities is ongoing, but the roadway is open to traffic.
The final invoice has been submitted for payment with the retainage payment due. Staff has reconciled all Heavy Civil costs and has determined that a Change Order in the amount of $7,548.96 is needed to close the construction contract.
RECOMMENDATION:
Approve Change Order No.1 in the amount of $7,548.96.
ALTERNATIVES:
Renegotiate final contract amount.
RESPONSIBLE STAFF:
Selena Griffett
COORDINATED WITH:
City Engineer
City Attorney
City Attorney
Fiscal Impact
- Budgeted Y/N:
- N
- Fiscal Year:
- 2024
- Account:
- 114-1111-519-6310
- Amount:
- 7,548.96
FISCAL IMPACT:
Funds to be allocated from Infrastructure Surtax
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Finance Department | Johnna Morris | 01/04/2024 10:41 AM |
| City Manager | Nick Mimms | 01/04/2024 10:48 AM |
- Form Started By:
- Selena Griffett
- Started On:
- 12/11/2023 11:08 AM
- Final Approval Date: