6.h.
Planning Board - 2:00 PM
Meeting Date:
10/13/2025
Re
PZSITE2025-00017 - 3898 SELVITZ RD-Precast Concrete Major Site Plan Amendment
Submitted For:
Kev Freeman

Information

SUBJECT:

PZSITE2025-00017
Major Site Plan Amendment
Precast Specialties LLC
3898 Selvitz Road

SUMMARY:

The petitioner is requesting approval of a phased site plan amendment. Phase 1 would include the construction of a batch plant. Phase 2 would include the expansion of an office / shop with associated site improvements. The property is working with FPUA to connect to water and sewer as part of the Phase 2 development.
The 75+/- acre parcel is currently used for the manufacturing of concrete products, for which concrete trucks currently haul the concrete for use in the manufacturing of products.
The petitioner wishes to obtain approval of an amendment to the previously approved site plan which would depict phasing, and the proposed improvement as noted:
Phase 1: Addition of Batch Plant with associated site improvements.
Phase 2: Addition of Office / Workshop with associated parking and site improvements.
 
Parcel Info:2432-500-0001-000-5
Owner PRECAST SPECIALITIES LLC
Site Address   3898 SELVITZ RD
Acres   75.00

The subject property has an existing Future Land Use designation of Heavy Industrial (HI) and an underlying Zoning designation of Heavy Industrial Zone (I-3). To the north of the subject parcel lies an industrial parcel. This parcel has a Future Land Use designation of Heavy Industrial (HI) and an underlying Zoning designation of Planned Development (PD). West of the subject parcel is another industrial site. This parcel has a Future Land Use designation of Heavy Industrial (HI) and an underlying Zoning designation of Heavy Industrial Zone (I-3). Precast Specialties South of the subject parcel lies right-of-way owned by North St. Lucie River Water Control District (NSLRWCD) followed by residential parcels.
 

RECOMMENDATION:

Based on findings that the proposal is in compliance with the Comprehensive Plan and that the proposal promotes the public health, safety and general welfare through site design and infrastructure improvements.

The proposed and revised application meets the standards of the City’s Code of Ordinances. Therefore, staff recommend the Planning Board forward the application, subject to the 8 conditions as noted, with a recommendation of APPROVAL to the City Commission.

If moved to the City Commission, all relevant documents will be updated to reflect the determination of the Planning Board.

Conditions:
  1. The timetable of development shall be such:
    • PHASE 1 START BY DATE COMPLETE BY DATE
      Batch Plant January 2026 December 2027
      Aggregate Bins/Wash Out January 2026 December 2027
      Treatment Pond January 2026 December 2027
      Dispatch Office/3 Parking Spaces January 2026 December 2027
      Landscaping/Wall January 2026 December 2027
    • PHASE 2 START BY DATE COMPLETE BY DATE
      Parking Lots and Lighting January 2028 December 2030
      Drainage Infrastructure January 2028 December 2030
      Water Main Extension/Hydrant January 2028 December 2030
      Grinder Station/Force Main January 2028 December 2030
      Removal of Temporary Trailers January 2028 December 2030
  2. A full calculation and proposed tree mitigation shall be approved by the city arborist prior to commencement of Phase 1.
  3. The property owner shall be responsible for maintenance of the trees through a landscape maintenance agreement. This responsibility includes the replacement of unhealthy and dead trees. The property owner shall submit to an on-site inspection of the planted/preserved vegetation 12 months after the issuance of the Phase 1 first certificate of occupancy. If it is determined that the planted vegetation is dead, diseased or otherwise not in compliance with provisions of this Code or the original approved tree mitigation plan, the property owner shall be provided notice and directed to correct any such deficiencies and replace all noncompliant materials within 60 days.
  4. No use shall exceed the applicable City of Fort Pierce standards for noise.
  5. The hours of operation of the facility shall be limited to: Monday – Friday between 6:30 a.m. to 8 p.m., Saturday – 7 a.m. to 8 p.m., Sunday – No operation. Quiet hours – 11p.m. to 7 a.m.
  6. The applicant shall implement the Heavy-Duty White Sound® Smart Reversing System alarm, or similar, to reduce, as far as practicable, the noise impact of reversing trucks and other equipment prior to completion of the Batch Plant within Phase 1.
  7. Prior to commencement of Phase 1, the applicant shall coordinate the approval of an Erosion and Sediment Control Plan with the City Engineer. The Plan shall relate to the sequence of construction of the development site, including stripping and clearing; rough grading; construction of utilities, infrastructure, and buildings; and final grading and landscaping. Sequencing shall identify the expected date on which clearing will begin, the estimated duration of exposure of cleared areas, areas of clearing, installation of temporary erosion and sediment control measures, and establishment of permanent vegetation. All erosion and sediment control measures necessary to meet the objectives of the city code of ordinances shall be maintained and in place throughout all phases of construction and after completion of development of the site.
  8. All applicable State and Federal permits shall be obtained before commencement of the development.

ALTERNATIVES:

Approval with alternative/additional conditions.

or

Denial

RESPONSIBLE STAFF:

Kev Freeman, Planning Director

COORDINATED WITH:

Technical Review Committee

Fiscal Impact

Budgeted Y/N:
N

OTHER INFORMATION:

N/A

Attachments

Form Review

Inbox Reviewed By Date
City Manager Alicia Rosenthal 10/08/2025 08:54 AM
Form Started By:
Kev Freeman
Started On:
10/07/2025 02:34 PM
Final Approval Date:
10/08/2025