7.b.
FPRA Regular Meeting
- Meeting Date:
- 04/08/2025
- Re
- Specific Authorization for design of 4th Floor Sunrise Event Center - ADC
- Submitted For:
- Shyanne Harnage
SUBJECT:
Approval of Specific Authorization 1 with Architects Design Collaborative, LLC. for design services of the 4th Floor of the Sunrise Center into a functional and attractive meeting and event venue in an amount not to exceed $22,500.00.
SUMMARY:
Staff requests authorization to proceed with Architects Design Collaborative, LLC, to develop a comprehensive design plan for transforming the 4th floor of the Sunrise Center into a functional and attractive meeting and event space. The design will prioritize functionality, aesthetics, and accessibility while incorporating modern, versatile elements to accommodate a variety of community events, including meetings, workshops, conferences, and social gatherings.
The scope of work includes the development of architectural schematic design documents for the interior build-out of an event center featuring a warming kitchen, restrooms, and lounge areas within approximately 9,000 square feet on the 4th floor of the Sunrise Center, located at 310 Orange Avenue, Fort Pierce, FL 34950.
The project fee shall not exceed $22,500.
The scope of work includes the development of architectural schematic design documents for the interior build-out of an event center featuring a warming kitchen, restrooms, and lounge areas within approximately 9,000 square feet on the 4th floor of the Sunrise Center, located at 310 Orange Avenue, Fort Pierce, FL 34950.
The project fee shall not exceed $22,500.
RECOMMENDATION:
Staff recommends approval.
ALTERNATIVES:
Staff will proceed as directed by the FPRA Board.
RESPONSIBLE STAFF:
Miriam Garcia, Redevelopment Specialist
COORDINATED WITH:
Shyanne Harnage, Community & Economic Development Director
Sara Hedges, City Attorney
Sara Hedges, City Attorney
Fiscal Impact
- Budgeted Y/N:
- y
- Fiscal Year:
- 2025
- Account:
- 104-9400-554-000-000
- Amount:
- 200,000
OTHER INFORMATION:
This project was allocated $200,000 in the FY2025 Project-Based Budget