7.e.
FPRA Special Meeting - 4:00 p.m.
- Meeting Date:
- 05/26/2020
- Re
- Fisherman's Wharf RFQ/P Revised Schedule
- Submitted For:
- Shyanne Helms
SUBJECT:
Fisherman's Wharf Redevelopment -- RFQ/P No. 2020-023
SUMMARY:
Due to the COVID-19 pandemic, all active solicitations were temporarily suspended. Staff received direction from the FPRA Board at the April 28, 2020 meeting to move forward with the Fisherman's Wharf RFQ/P. The new schedule is as follows:
RFQ Release Date: June 3, 2020
Pre-Bid Meeting: June 24, 2020
RFQ Submittal Due: July 8, 2020
Shortlist Review by FPRA Board: July 28, 2020
RFP Issued to Shortlist: August 3, 2020
RFP Closing Date: October 5, 2020
RFQ Release Date: June 3, 2020
Pre-Bid Meeting: June 24, 2020
RFQ Submittal Due: July 8, 2020
Shortlist Review by FPRA Board: July 28, 2020
RFP Issued to Shortlist: August 3, 2020
RFP Closing Date: October 5, 2020
RECOMMENDATION:
Staff recommends the acceptance of the proposed RFQ/RFP schedule.
ALTERNATIVES:
Staff will proceed as directed by the FPRA Board.
RESPONSIBLE STAFF:
Shyanne Helms, Communications + Economic Development Manager
Evaluation Committee:
Jack Andrews, City Engineer
Jennifer Hofmeister, Planning Director
Paul Thomas, Building Official
Dean Kubitschek, Marina Manager
Stan Payne, St. Lucie County Port Director
Evaluation Committee:
Jack Andrews, City Engineer
Jennifer Hofmeister, Planning Director
Paul Thomas, Building Official
Dean Kubitschek, Marina Manager
Stan Payne, St. Lucie County Port Director
COORDINATED WITH:
Purchasing Division
Fiscal Impact
OTHER INFORMATION:
N/A