Re
Approval of Specific Authorization No. 2 - Culpepper & Terpening, Inc - Avenue B Reconstruction, Ref. RFQ No. 2019-027
Submitted For:
John Andrews

SUBJECT:

Approval of Specific Authorization No. 2 to Culpepper & Terpening, Inc (C&T) in an amount not to exceed $62,970.00. Pending City Attorney approval.

SUMMARY:

Project limits are Avenue B from 8th Street to 13th Streeet. Improvements under this project will include roadway reconstruction, sidewalks, curb & gutter and driveway aprons. FPUA will also be updating their faclities in the project limits. The design costs have been negiotiated with C&T to provide construction plans and bid specifications for the proposed reconstruction work. This authorization will be funded by Infrastructure Surtax funds.  A copy of the specific authorization is attached including itemized scope of work. 

RECOMMENDATION:

Approval

ALTERNATIVES:

Reject the proposal and start negotiations with the next continuing service provider under RFQ 2019-027.

RESPONSIBLE STAFF:

Edward Seissiger, Engineering Project Manaager

COORDINATED WITH:

Stef Mathes, Senior Vice President- Culpepper & Terpening.

Fiscal Impact

Budgeted Y/N:
y
Fiscal Year:
2019/20
Account:
100-1111-519-6321
Amount:
$62,970.00

FISCAL IMPACT:

C&T design proposal will be funded by SUR tax funds

Attachments

Form Review

Inbox Reviewed By Date
Finance Department Johnna Morris 08/03/2020 11:39 AM
City Manager Nick Mimms 08/04/2020 12:27 PM
Form Started By:
eseissiger
Started On:
07/27/2020 08:13 AM
Final Approval Date:
08/04/2020