Agenda Item # 11.b.
City Commission Regular Meeting - 4:30 pm
Meeting Date:
09/20/2021
Re
Award of Porpoise Avenue Beach Access Parking Lot Improvements Construction Contract to Pav-Co Contracting, Inc. - Bid No. 2021-036
Submitted For:
John Andrews

SUBJECT:

Approve award of the Bid No. 2021-036, Porpoise Avenue Beach Access Parking Improvements construction contract to the low bidder, PavCo Contracting, Inc., in an amount not to exceed $290,479.29.

SUMMARY:

The construction project proposes the reconfiguration of the the existing parking area along with the expansion of the parking lot to the west as indicated on the attached plan.  Improvements will include a pervious paver parking area complete with a new exit driveway connection onto South Ocean Drive, landscaping installation, and an irrigation system.  Construction approvals for the proposed work have been granted from both FDEP and FDOT.  

RECOMMENDATION:

Staff recommends approval

ALTERNATIVES:

Re-bid the project

RESPONSIBLE STAFF:

Engineering

COORDINATED WITH:

SLC Coastal Engineer
FP Public Works Director

Fiscal Impact

Budgeted Y/N:
Y
Fiscal Year:
FY 20/21
Account:
108-1111-519-6320
Amount:
$290,479.29

FISCAL IMPACT:

The construction cost will be funded from the SLC Park Municipal Service Tax Unit in an amount of $290,479.29.

Attachments

Form Review

Inbox Reviewed By Date
Finance Department Johnna Morris 09/10/2021 10:07 AM
City Manager Nick Mimms 09/10/2021 01:35 PM
Form Started By:
Tracy Telle
Started On:
09/03/2021 04:14 PM
Final Approval Date: