- Approval of Dickerson FL, Inc. C.O. No. 1 - S. 5th Street Roadway Improvements - Ref. Bid No. 2021-024
- Submitted For:
- John Andrews
SUBJECT:
Approval of Dickerson Florida, Inc. C.O. No. 1 in the amount of $41,027.68 providing compensation for additional work on the S. 5th Street Roadway Improvement project.
SUMMARY:
The original construction limits extended between Delaware Avenue and Boston Avenue. During construction, FPUA and other communication contractors had to extend through the Boston Avenue intersection to complete their underground service connections. Due to the extensive amount of restoration work it was determined that the area would be better suited to extend the construction limits through this work zone with FPUA contributing to the cost of the road work.
RECOMMENDATION:
Staff recommends approval
ALTERNATIVES:
Deny and leave intersection with numerous asphalt patches and substandard ADA curb ramps.
RESPONSIBLE STAFF:
Engineering
COORDINATED WITH:
FPUA
Fiscal Impact
- Budgeted Y/N:
- N/A
- Fiscal Year:
- FY 21/22
- Account:
- 110-1111-519-6310
- Amount:
- $41,027.68
FISCAL IMPACT:
Initial funding of $41,027.68 shall be encumbered from Road and Bridge Impact Fees, Account No. 110-1111-519-6310, with an FPUA reimbursement of $26,725 providing for a net required City funding of $14,302.68.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Finance Department | Johnna Morris | 03/30/2022 11:47 AM |
| City Manager | Nick Mimms | 03/30/2022 01:47 PM |
- Form Started By:
- Tracy Telle
- Started On:
- 03/18/2022 08:28 AM
- Final Approval Date:
- 03/30/2022