VIOLATIONS:
FBC 105.1 (2017) Permit Required
FINDINGS/ORDER:
Order Determining Violation - August 18, 2021
Notice of Extension of Time (90 days) - October 20, 2021
Affidavit of Non-Compliance - March 31, 2022
Order Assessing Fine and Imposing Lien - September 15, 2022
Affidavit of Compliance - February 9, 2023
Notice of Extension of Time (90 days) - October 20, 2021
Affidavit of Non-Compliance - March 31, 2022
Order Assessing Fine and Imposing Lien - September 15, 2022
Affidavit of Compliance - February 9, 2023
ACTION DATES:
1. August 17, 2021 - Special Magistrate Hearing - owner was provided 60 days to get/renew the permit or fines may accrue.
2. October 20, 2021 - A Notice of Extension of Time (90 days) was recorded.
3. March 30, 2022 - An Affidavit of Non-Compliance was recorded (3/31/2022) and fines began to accrue.
4. September 15, 2022 - An Order Assessing Fine and Imposing Lien was prepared and recorded on September 20, 2022.
5. February 9, 2023 - the roof permit was renewed and the provided engineer's letter satisfied the final inspection and the permit was closed. An Affidavit of Compliance was recorded and fines stopped on this date. The fines/lien total: $31,650.00 including $50.00 of recording fees.
6. February 13, 2023 - a lien reduction request was received by the Building Department.
2. October 20, 2021 - A Notice of Extension of Time (90 days) was recorded.
3. March 30, 2022 - An Affidavit of Non-Compliance was recorded (3/31/2022) and fines began to accrue.
4. September 15, 2022 - An Order Assessing Fine and Imposing Lien was prepared and recorded on September 20, 2022.
5. February 9, 2023 - the roof permit was renewed and the provided engineer's letter satisfied the final inspection and the permit was closed. An Affidavit of Compliance was recorded and fines stopped on this date. The fines/lien total: $31,650.00 including $50.00 of recording fees.
6. February 13, 2023 - a lien reduction request was received by the Building Department.
RECOMMENDATION: