Agenda Item # 11.b.
City Commission Regular Meeting
Meeting Date:
06/05/2023
Re
Piggyback FPUA Contract with Mastec Avenue B Dry Utility Installation
Submitted For:
Gelencia Carter

SUBJECT:

Approval to Piggyback the FPUA Contract with Mastec North America, Inc. and a Purchase Order in the amount of $273,561.36 to install conduits and related fixtures for AT&T and Comcast for the Avenue B Roadway Construction Project.

SUMMARY:

Staff requested a cost proposal from the prime Contractor Heavy Civil, and from Mastec. Heavy Civil cost proposal for this additional work was $367,845.00. Mastec's proposal for this work is $273,561.36. Mastec will be performng the FPUA underground relocations for the project.

RECOMMENDATION:

Staff is requesting approval of a Purchase Order in the amount of $273,561.36 be issued to Mastec, Piggybacking FPUA unit price contract with Mastec, to perform the installation of conduits and related fixtures for AT&T and Comcast.

ALTERNATIVES:

The City may award a Change Order to Heavy Civil Inc, in the amount of $367,845.00 or the CIty could issue an RFQ for additional dry utility work delaying the project by a minimum of 90 days.

RESPONSIBLE STAFF:

Selena Griffett, Project Engineer

COORDINATED WITH:

City Engineer
Purchasing

Fiscal Impact

Budgeted Y/N:
N
Fiscal Year:
2023
Account:
114-1111-519-6310
Amount:
$273,561.36

OTHER INFORMATION:

Funds to be provided by the Infrastructure Surtax Account 114-1111-519-6310

Attachments

Form Review

Inbox Reviewed By Date
Finance Department Johnna Morris 05/19/2023 02:26 PM
City Manager Nick Mimms 05/24/2023 09:29 AM
Finance Department Johnna Morris 05/30/2023 11:12 AM
City Manager Nick Mimms 05/31/2023 07:39 AM
Form Started By:
gmontgomery
Started On:
05/18/2023 04:38 PM
Final Approval Date:
05/31/2023