Skip to main content

AgendaQuick™

View Agenda Item

Agenda Item # 11.h.
City Commission Regular Meeting - 5:05 pm
Meeting Date:
10/16/2023
Re
Approval of PRP Construction CO No. 1 - Ohio Avenue Roadway Improvements - Ref. Bid No. 2023-035
Submitted For:
John Andrews

SUBJECT:

Approval of PRP Construction Group, LLC Change Order No. 1 in the amount of $110,250.00.

SUMMARY:

The Ohio Avenue Roadway Reconstruction project extends between U.S. Highway 1 and 11th Street a distance of one-half mile.  The project includes new potable water, sanitary sewer upgrades, storm drainage facilities, sidewalks, and complete roadway reconstruction.  The project was awarded to PRP Construction at the June 5, 2023, City Commission meeting.  The original award did not include streetlight conduit and handhole installation as staff intended to contract with FPUA to complete this work.  However, due to their contractor's workload they have requested that our contractor provide the required labor services for the proposed streetlighting installation along this corridor.  

RECOMMENDATION:

Staff recommends approval.

ALTERNATIVES:

Request quotes from other vendors which will result in delaying the construction commencement of the roadway project.

RESPONSIBLE STAFF:

Engineering

COORDINATED WITH:

FPUA Electric

Fiscal Impact

Budgeted Y/N:
N/A
Fiscal Year:
FY 23/24
Account:
114-1111-563-100
Amount:
$110,250.00

FISCAL IMPACT:

Funding of the $110,250.00 shall be encumbered from the Surtax proceeds, Account No. 114-1111-563-100.

Attachments

Form Review

Inbox Reviewed By Date
Finance Department Karen Logue 10/10/2023 05:17 PM
City Manager Nick Mimms 10/10/2023 06:27 PM
Form Started By:
Tracy Telle
Started On:
10/03/2023 04:05 PM
Final Approval Date:
10/10/2023