6.b.
Planning Board
- Meeting Date:
- 12/11/2023
- Re
- Site Plan (Development and Design Review) - Viva West - 3037 S. Jenkins Road
Information
SUBJECT:
Site Plan (Development and Design Review) - Viva West - 3037 S. Jenkins Road
SUMMARY:
The applicant is requesting the review and approval of an application for a Site Plan (Development and Design Review) for a two-hundred and twenty-two (222) unit rental community at 3037 S. Jenkins Road. The community will consist of one-bedroom, two-bedroom and three-bedroom duplexes as well as two-bedroom row houses. Viva East is the sister project to Viva West. Both communities will share access to amenities such as a fitness center, business lodge, community room, catering kitchen, pet spa, outdoor grilling areas and more.
The proposed development is located on a parcel with an approximate acreage of 27.89 acres. The future land use of the parcel is Medium Density Residential, RM, and the zoning is Medium Density Residential, R-4.
The proposed development is located on a parcel with an approximate acreage of 27.89 acres. The future land use of the parcel is Medium Density Residential, RM, and the zoning is Medium Density Residential, R-4.
RECOMMENDATION:
Staff's recommendation is for the Planning Board to move the proposed Site Plan (Development and Design Reviews), with four conditions, for approval to City Commission.
- A completion certification by a landscape architect, cost estimate and landscape bond pursuant to City Code 123-6 shall be required before the Final Certificate of Occupancy is approved for the site.
- A gopher tortoise survey will be required per State Statute before construction can begin.
- Addresses will need to be submitted to the Planning Department for all units prior to building permit applications.
- Prior to the issuance of any Site Clearing Permits, the applicant shall provide a Tree Mitigation Survey and coordinate with the City of Fort Pierce Arborist for the required mitigation of the City-regulated trees proposed to be removed as a result of this site's development/construction activity.
ALTERNATIVES:
- Recommendation of approval with alternative conditions
- Recommendation of disapproval
RESPONSIBLE STAFF:
Ryan Altizer, Senior Planner
COORDINATED WITH:
Technical Review Committee
Fiscal Impact
OTHER INFORMATION:
N/A
Attachments
Form Review
- Form Started By:
- raltizer
- Started On:
- 12/04/2023 03:40 PM
- Final Approval Date:
- 12/04/2023