7.a.
FPRA Regular Meeting - 5:05 p.m.
- Meeting Date:
- 04/09/2024
- Re
- Approval of Change Order No. 1 - General Contractor Services, Exterior Restoration of Old St. Anastasia for the amount of $98,414.60
- Submitted For:
- Nick Mimms
SUBJECT:
Approval of Change Order No. 1 - General Contractor Services, Exterior Restoration of Old St. Anastasia for the amount of $98,414.60.
SUMMARY:
During the FPRA Meeting on February 13, 2024, the Board received a presentation detailing the outcomes of the Old St. Anastasia conditions assessment. Subsequently, the Board requested additional services for the exterior restoration of Old St. Anastasia. These services encompass the removal of the fire escape, replacement of the north flat roof, and other related tasks. These additional services will necessitate a revision of the project's scope and will require a change order approval by the FPRA Board. The inclusion of Innovative Masonry Restoration, LLC's added services will increase the current budget by $98,414.60. Approval of the change order will increase the overall budget from $588,168.46 to $686,583.06.
RECOMMENDATION:
Staff recommends approval of the change order.
ALTERNATIVES:
Staff will proceed as directed by the Board.
RESPONSIBLE STAFF:
Marsha Commond, Redevelopment Specialist
COORDINATED WITH:
N/A
Fiscal Impact
- Budgeted Y/N:
- Y
- Fiscal Year:
- 2023/2024
- Account:
- 1049400-562100
- Amount:
- 98,414.60
OTHER INFORMATION:
N/A