Agenda Item # 11.h.
City Commission Regular Meeting - 5:05 pm
- Meeting Date:
- 08/05/2024
- Re
- Approval of Continuing Services Contract for Miscellaneous Professional Services Provider - Cape Design Engineering, Co.
- Submitted For:
- Gelencia Carter
SUBJECT:
Approval of Continuing Services Contract for RFQ No. 2024-005, Miscellaneous Professional Architectural and Engineering Services to Cape Design Engineering, Co., Melbourne, FL.
SUMMARY:
During the February 20, 2024, City Commission meeting, RFQ No. 2024-005 was awarded to twelve firms. These firms were selected as the city's Miscellaneous Professional Continuing Services providers. They are licensed professional consultants and will offer services in areas such as Architectural, Environmental Services, Facilities Engineering - MEP Services, Facilities Engineering - Structural, Hydrogeological, Landscape Architect, and Urban Planning.
The firms operate under regulations outlined in Chapter 287.055 of the Florida Statues, known as the Consultant's Competitive Negotiation Act (CCNA). They will provide advice, technical investigation, analysis, design, and other professional services to support all city departments for an initial term of one (1) year, with three (3) one-year renewal options.
The firms operate under regulations outlined in Chapter 287.055 of the Florida Statues, known as the Consultant's Competitive Negotiation Act (CCNA). They will provide advice, technical investigation, analysis, design, and other professional services to support all city departments for an initial term of one (1) year, with three (3) one-year renewal options.
RECOMMENDATION:
Staff recommends approval.
ALTERNATIVES:
Staff will proceed as directed by the Commission.
RESPONSIBLE STAFF:
Shyanne Harnage, Economic Development Manager
Audria V. Moore, Special Projects Coordinator
Audria V. Moore, Special Projects Coordinator
COORDINATED WITH:
Nicholas C. Mimms, P.E., ICMA-CW, City Manager
Johnna Morris, Director of Finance
Johnna Morris, Director of Finance
Fiscal Impact
- Budgeted Y/N:
- Y
- Fiscal Year:
- 2024
- Account:
- N/A
- Amount:
- N/A
OTHER INFORMATION:
No fiscal impact at this time. Each individual project will be presented on a project-by-project basis.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Finance Department | Johnna Morris | 07/23/2024 12:08 PM |
| City Manager | Nick Mimms | 07/23/2024 02:07 PM |
- Form Started By:
- Gelencia Carter
- Started On:
- 07/22/2024 05:22 PM
- Final Approval Date:
- 07/23/2024