Approval of Change Order No. 8 Journey C & D Group, Inc.
Submitted For:
Audria Moore

SUBJECT:

Approval of Change Order No. 8 to General Contractor Services-Highway Museum in an amount not to exceed $9,569.15 for the City of Fort Pierce Florida Highwaymen Museum renovation project.

SUMMARY:

The original budget for the bathroom and kitchen plumbing was $10,700. Change Order 4 for the bathroom renovation included an additional $4,700 for plumbing improvements, raising the total to $15,400. The final plumbing contract amounts to $23,250, resulting in a difference of $7,850. This difference is due to unforeseen circumstances, as there were no construction drawings available at the time of the bid.

 

RECOMMENDATION:

Staff recommends approval of Changer Order No. 8 to General Contractor Services-Highway Museum in an amount not to exceed $9,569.15 for unexpected additional plumbing costs.

ALTERNATIVES:

Staff will proceed as directed by the FPRA Board.

RESPONSIBLE STAFF:

Audria V. Moore, Special Projects Coordinator

COORDINATED WITH:

Richard Stauffer, Facilities Manager
Journey C&D Group, Inc.

Fiscal Impact

Budgeted Y/N:
Y
Fiscal Year:
2025
Account:
1049400-563200
Amount:
$9,569.15

OTHER INFORMATION:

The change order not to exceed $9,569.15 will be funded by FPRA Account Number:1049400-563200 - Other improvements.

Attachments