7.b.
FPRA Regular Meeting
- Meeting Date:
- 02/11/2025
- Re
- Approval of Change Order No. 12 Journey C & D Group, Inc.
- Submitted For:
- Audria Moore
SUBJECT:
Approval of Change Order No. 12 for General Contractor Services, Journey C & D Group, Inc. in an amount not to exceed $45,654.20 for the City of Fort Pierce Florida Highwaymen Museum renovation project to correct the parking lot elevation to prevent water intrusion.
SUMMARY:
The proposed change involves re configuring the parking lot at 1234 Avenue D to prevent water intrusion into the first floor and to install new asphalt.
RECOMMENDATION:
Staff recommends approval of Change Order No. 12 to General Contractor Services for the Highway Museum, in an amount not to exceed $45,654.20, to cover parking lot drainage and new asphalt.
ALTERNATIVES:
Staff will proceed as directed by the FPRA Board.
RESPONSIBLE STAFF:
Audria V. Moore, Special Projects Coordinator
COORDINATED WITH:
John Andrews, Deputy City Manager/City Engineer
Journey C&D Group, Inc.
Journey C&D Group, Inc.
Fiscal Impact
- Budgeted Y/N:
- n
- Fiscal Year:
- 2025
- Account:
- 104-9400-554-000-00
- Amount:
- $45,654.20
OTHER INFORMATION:
The change order not to exceed $45,654.20 will be funded by FPRA Account Number Improvements - Other Improvements - #104-9400563200.