7.b.
FPRA Regular Meeting
Meeting Date:
02/11/2025
Re
Approval of Change Order No. 12 Journey C & D Group, Inc.
Submitted For:
Audria Moore

SUBJECT:

Approval of Change Order No. 12 for General Contractor Services, Journey C & D Group, Inc. in an amount not to exceed $45,654.20 for the City of Fort Pierce Florida Highwaymen Museum renovation project to correct the parking lot elevation to prevent water intrusion.

SUMMARY:

The proposed change involves re configuring the parking lot at 1234 Avenue D to prevent water intrusion into the first floor and to install new asphalt.

RECOMMENDATION:

Staff recommends approval of Change Order No. 12 to General Contractor Services for the Highway Museum, in an amount not to exceed $45,654.20, to cover parking lot drainage and new asphalt.

ALTERNATIVES:

Staff will proceed as directed by the FPRA Board.

RESPONSIBLE STAFF:

Audria V. Moore, Special Projects Coordinator

COORDINATED WITH:

John Andrews, Deputy City Manager/City Engineer
Journey C&D Group, Inc.

Fiscal Impact

Budgeted Y/N:
n
Fiscal Year:
2025
Account:
104-9400-554-000-00
Amount:
$45,654.20

OTHER INFORMATION:

The change order not to exceed $45,654.20 will be funded by FPRA Account Number Improvements - Other Improvements - #104-9400563200.