Agenda Item # 11.G.
City Commission Regular Meeting - 5:05 PM
Meeting Date:
05/18/2026
Re
Time Extension for FDOT Agreement G-2X21 for Avenue D Improvements
Submitted For:
Mark Zrallack

SUBJECT:

Approve and execute the Supplemental Agreement No. 1 to FDOT Contract G-2X21 for a time extension to December 31, 2027. 

SUMMARY:

FDOT Agreement G-2X21 was fully executed on April 29, 2024 and provided $1.5 million in General Appropriation Act grant funding for the construction of the Avenue D Improvements from N 29th Street to US 1. Agreement G-2X21 has an expiration date of June 30, 2026. Staff has coordinated with FDOT to obtain a time extension for construction activities to be completed by December 31, 2027.

The current Notice to Proceed for the contractor to begin work on the Avenue D project is May 26, 2026. The current construction completion date is February 18, 2027. 

RECOMMENDATION:

Staff recommends approval and execution of the Supplemental Agreement for G-2X21.

ALTERNATIVES:

Do not execute the Supplemental Agreement. Note that the Grant funding will be relinquished.

RESPONSIBLE STAFF:

Selena Griffett
Mark Zrallack

COORDINATED WITH:

FDOT
City Attorney

Fiscal Impact

Budgeted Y/N:
Y
Fiscal Year:
2026
Account:
11411115631000
Amount:
$4,072,873.50

FISCAL IMPACT:

The amount shown is currently encumbered on PO 260658 awarded to CW Roberts Contracting for the construction of the Avenue D Improvements.